Monthly Project Status Report July 2023 – Issue 91
Monthly Status Update.
Download PDF →June Monthly Project Updates
Monthly Status Update.
Download PDF →May Monthly Project Updates
Monthly Status Update.
Download PDF →4k, 5k, 6k Restroom & Drinking Fountain ADA Upgrades – 05-12-23 Weekly Construction Update
Work this week: The contractor completed installation of plumbing fixtures, restroom accessories and toilet partitions in Building 6200 restrooms. Access hatches and lighting fixtures are scheduled to be installed next week.
Download PDF →4k, 5k, 6k Restroom & Drinking Fountain ADA Upgrades – 05-05-23 Weekly Construction Update
Work this week: The contractor completed tile floor installation. Plumbing fixtures are currently being installed.
Download PDF →April Monthly Project Updates
Monthly Status Update.
Download PDF →4k, 5k, 6k Restroom & Drinking Fountain ADA Upgrades – 04-28-23 Weekly Construction Update
Work this week: The contractor finished installing wall tile and floor sealer in the 6200 restrooms. Grout and floor tile will begin on Monday May 1, 2023.
Download PDF →4k, 5k, 6k Restroom & Drinking Fountain ADA Upgrades – 04-14-23 Weekly Construction Update
Work this week: Contractor hung, taped and painted lids in 6200 men’s and women’s restrooms. New wall at drinking fountain alcove has been insulated and began floating walls are in preparation for tile.
Download PDF →4k, 5k, 6k Restroom & Drinking Fountain ADA Upgrades – 04-07-23 Weekly Construction Update
Work this week: Contractor has completed fire caulking overhead bracing and installed lath at Building 6200. Lids have also been hung in the men’s restroom.
Download PDF →March Monthly Project Updates
Monthly status update.
Download PDF →