9100 Roofing and HVAC – 04-22-22 Weekly Construction Update
Work this week: Contractor completed Test and Balance work. Punchlist work is in progress. The project is now substantially complete.
Download PDF →9100 Roofing and HVAC – 04-15-22 Weekly Construction Update
Work this week: Contractor completed the plenum and duct work on the vehicle exhaust fan and electrical connections to all new HVAC equipment.
Download PDF →9100 Roofing and HVAC – 04-08-22 Weekly Construction Update
Work this week: Contractor installed new parapet cleats and coping, as well as a new sheet metal cap on the exhaust fan curb. Downspout installation work remains ongoing.
Download PDF →9100 Roofing and HVAC – 04-01-22 Weekly Construction Update
Work this week: HVAC equipment installation work remains ongoing. Downspout installation work is in progress.
Download PDF →April 2022 Monthly Project Update – 9100 2nd Issuance
Monthly status update on 2nd Issuance Building 9100 Measure L projects.
Download PDF →9100 Roofing and HVAC – 03-25-22 Weekly Construction Update
Work this week: The contractor completed the roofing portion of work. The HVAC equipment installation remains ongoing.
Download PDF →9100 Roofing and HVAC – 03-18-22 Weekly Construction Update
Work this week: The roofing installation work is ongoing. New parapet wall framing, and substrate were installed. The gutter and downspout installation began.
Download PDF →9100 Roofing and HVAC – 03-11-22 Weekly Construction Update
Work this week: The roofer contractor began installing the new roofing system. New roof hatch was installed.
Download PDF →March 2022 Monthly Project Update
Monthly status update on all existing Measure L projects.
Download PDF →February 2022 Monthly Project Update
Monthly status update on all existing Measure L projects.
Download PDF →