Category: SLO HVAC/Roofs Phase 2

Chiller Replacement – 12-2-22

December 2, 2022 · SLO HVAC/Roofs Phase 2

Work this week: Contractor began replacing existing pumps. One chiller unit was removed/replaced. Chiller yard is currently running on a mobile chiller, so there are no interruptions at this time.

Download PDF →

SLO 6100, 6300, and 7100 Roofing and HVAC – 09-09-22 Weekly Construction Update

September 9, 2022 · SLO HVAC/Roofs Phase 2

Work this week: Doghouses for new ductwork are being installed and insulation for refrigerant lines and boiler piping are in progress. HVAC controls are in the process of being programmed.

Download PDF →

July Monthly Project Updates

July 31, 2022 · District Wide Upgrades 2nd, SLO HVAC/Roofs Phase 2, Upgrades - Aquatic Center

Monthly status update.

Download PDF →

SLO 6100, 6300, and 7100 Roofing and HVAC – 07-08-22 Weekly Construction Update

July 15, 2022 · SLO HVAC/Roofs Phase 2

Work this week: The roofing & HVAC duct installation work remains on going.

Download PDF →

SLO 6100, 6300, and 7100 Roofing and HVAC – 07-08-22 Weekly Construction Update

July 8, 2022 · SLO HVAC/Roofs Phase 2

Work this week: The roofing, duct installation, and sheet metal cap installation work is currently in progress.

Download PDF →

June Monthly Project Updates

June 30, 2022 · District Wide Upgrades 2nd, SLO HVAC/Roofs Phase 2, Upgrades - Aquatic Center

Monthly status update.

Download PDF →

SLO 2500 Roofing Replacement — 06-03-22 Weekly Construction Update

June 3, 2022 · SLO HVAC/Roofs Phase 2

 Work this week: Contractor is installing parapet caps. TPO roofing installation is near completion. 

Download PDF →

SLO 6100, 6300, and 7100 Roofing and HVAC – 05-20-22 Weekly Construction Update

May 20, 2022 · SLO HVAC/Roofs Phase 2

Work this week: Electrical disconnect switch and power were run to the rooftop packaged HVAC unit serving classroom 6301. Ductwork installation is nearing completion.

Download PDF →

SLO 6100, 6300, and 7100 Roofing and HVAC – 05-13-22 Weekly Construction Update

May 13, 2022 · SLO HVAC/Roofs Phase 2

Work this week: Condensate and gas lines were connected to the rooftop packaged HVAC unit serving classroom 6301.

Download PDF →

SLO 6100, 6300, and 7100 Roofing and HVAC – 05-06-22 Weekly Construction Update

May 6, 2022 · SLO HVAC/Roofs Phase 2

Work this week: The rooftop HVAC unit serving classroom 6301 was delivered and set on the roof.

Download PDF →
Older Posts →
  • Search News:

    Search the Cuesta College Bond Website:
  • News Categories

    • Articles
    • Construction Updates
      • 9100 Roofing-HVAC
      • District Wide Asphalt
      • District Wide Upgrades
      • District Wide Upgrades 2nd
      • District-Wide Wayfinding
      • EV Charging Stations
      • Hollister Adobe Stabilization
      • Interim Housing
      • NCC Early Childhood Education Center
      • NCC Parking Lot 10 and Monument Sign
      • North County Campus Center
      • North County Sitework
      • Planning – Aquatic Center
      • Repairs – HVAC/Roofs 1100, 4500, and 4600
      • SLO 1000 Complex Renovations
      • SLO 2000 Complex Renovations
      • SLO Campus Instructional Building
      • SLO Data Center
      • SLO HVAC/Roofs Phase 1
      • SLO HVAC/Roofs Phase 2
      • SLO Switchgear Replacement
      • Technology Upgrades 2nd
      • Technology Upgrades 3rd
      • Upgrades – Aquatic Center
    • Press Releases
    • Uncategorized

Back To Top

Cuesta College Logo
Search the Cuesta College Bond Website: