Chiller Replacement – 03-31-23
Work this week: Contractor has installed all three chillers. Electrical cut over has been completed. Manufacturer is scheduled to begin start up this week.
Download PDF →Chiller Replacement – 12-2-22
Work this week: Contractor began replacing existing pumps. One chiller unit was removed/replaced. Chiller yard is currently running on a mobile chiller, so there are no interruptions at this time.
Download PDF →SLO 6100, 6300, and 7100 Roofing and HVAC – 09-09-22 Weekly Construction Update
Work this week: Doghouses for new ductwork are being installed and insulation for refrigerant lines and boiler piping are in progress. HVAC controls are in the process of being programmed.
Download PDF →July Monthly Project Updates
Monthly status update.
Download PDF →SLO 6100, 6300, and 7100 Roofing and HVAC – 07-08-22 Weekly Construction Update
Work this week: The roofing & HVAC duct installation work remains on going.
Download PDF →SLO 6100, 6300, and 7100 Roofing and HVAC – 07-08-22 Weekly Construction Update
Work this week: The roofing, duct installation, and sheet metal cap installation work is currently in progress.
Download PDF →June Monthly Project Updates
Monthly status update.
Download PDF →SLO 2500 Roofing Replacement — 06-03-22 Weekly Construction Update
Work this week: Contractor is installing parapet caps. TPO roofing installation is near completion.
Download PDF →SLO 6100, 6300, and 7100 Roofing and HVAC – 05-20-22 Weekly Construction Update
Work this week: Electrical disconnect switch and power were run to the rooftop packaged HVAC unit serving classroom 6301. Ductwork installation is nearing completion.
Download PDF →SLO 6100, 6300, and 7100 Roofing and HVAC – 05-13-22 Weekly Construction Update
Work this week: Condensate and gas lines were connected to the rooftop packaged HVAC unit serving classroom 6301.
Download PDF →