SLO Campus Center (DSA) – 05-17-24 – Weekly Construction Update
Monthly Project Status Report September 2023 – Issue 93
April Monthly Project Update – SLO Campus RR & Drinking Fountain ADA Upgrades
Monthly status update on SLO Campus Restrooms/Drinking Fountain ADA Upgrades projects.
Download PDF →Early Childhood Education – 03-22-19 Weekly Construction Update
Work this week: Despite the rain, the well subcontractor was able prep the existing well for abandonment...
Download PDF →SLO Instructional Building – 04-28-17 Weekly Construction Update
Work this week: The building’s fire line was installed and has passed inspection...
Download PDF →SLO Instructional Building – 02-24-17 Weekly Construction Update
Work this week: The fire sprinkler rough-in is 90% complete on the first floor...
Download PDF →Cuesta College holds ‘topping out’ ceremony at new North County Campus Center (video)
One of the last beams is moved into place on the steel frame of a new structure at Cuesta College's North Campus campus on Nov. 8, 2016. The new center will house a variety of student services as well as...
Read More →North County Campus Center – 8-26-16 Weekly Construction Update
Work this week: The plumbing and electrical contractors are continuing layout, excavation, installation, testing and backfill of under slab pipe and conduit, with the under slab waste pipe nearing completion...
Download PDF →Project Status Report – January 2016
Status report for various First Issuance Projects for January 2016.
Download PDF →Measure L Bond Team
At the December 2, 2015, Cuesta College Board of Trustees meeting, the many individuals involved with facilitating the Measure L work gathered for a photo opportunity with members of the Board. Team members included employees of Blach Construction, Kitchell CEM, PMSM...
Read More →