Cuesta College Bond Info

  • About Measure L
    • General Info
    • Ballot Language
    • Frequently Asked Questions
  • Project Info
    • Project Overview
    • Projects: 1st Issuance
    • Projects: 2nd Issuance
    • Projects: 3rd Issuance
    • Featured Image Gallery
    • Construction Alerts
    • SLO Campus Map
    • North County Map
  • Oversight Committee
  • Business Opportunities
    • Contractor Prequalification
    • Business RFQs/RFPs
    • Bid Timelines
    • Online Plan Room
  • News
  • Contact

Category: Construction Updates

February Monthly Project Updates

February 28, 2023 · District Wide Upgrades 2nd

Monthly status update.

Download PDF →

4k, 5k, 6k Restroom & Drinking Fountain ADA Upgrades – 02-24-23 Weekly Construction Update

February 24, 2023 · District Wide Upgrades 2nd

Work this week: Framing is ongoing in 6200 restrooms and NCM is currently correcting punch list items in 4200/4300/5100/6100.

Download PDF →

4k, 5k, 6k Restroom & Drinking Fountain ADA Upgrades – 02-17-23 Weekly Construction Update

February 17, 2023 · District Wide Upgrades 2nd

Work this week: Additional demo has been performed in 6200 restrooms, and framing is proceeding. Fire alarm has been tested in 4200/4300 restrooms, and NCM is currently correcting punch list items in 4200/4300/5100/6100.

Download PDF →

SLO Electrical Building Switchgear Replacement – 02-17-23 Weekly Construction Update

February 17, 2023 · SLO Switchgear Replacement

Work this week: Roof framing is on hold pending arrival of new 4x6” nailers, which should be here this week. NCM is currently laying base in preparation for concrete flatwork which will be poured this week.

Download PDF →

4k, 5k, 6k Restroom & Drinking Fountain ADA Upgrades – 02-10-23 Weekly Construction Update

February 10, 2023 · District Wide Upgrades 2nd

Work this week: Contractor is preparing 5100 restrooms for final punch. 6200 framing is ongoing.

Download PDF →

4k, 5k, 6k Restroom & Drinking Fountain ADA Upgrades – 02-03-23 Weekly Construction Update

February 3, 2023 · District Wide Upgrades 2nd

Work this week: Contractor installed door hardware in 5100, and touchup work is being performed. Punch list will be scheduled after touchup work has been completed. MEP rough-in for 6200 is currently in progress. Punch list has been issued for...

Download PDF →

January Monthly Project Updates

January 31, 2023 · District Wide Upgrades 2nd, SLO Switchgear Replacement

Monthly status update.

Download PDF →

4k, 5k, 6k Restroom & Drinking Fountain ADA Upgrades – 01-27-23 Weekly Construction Update

January 27, 2023 · District Wide Upgrades 2nd

Work this week: Construction at 4300 restrooms is substantially complete and punch walk has been performed. Plumbing and framing work in 6200 is currently in progress. Building 5100 is awaiting signage and door hardware.

Download PDF →

4k, 5k, 6k Restroom & Drinking Fountain ADA Upgrades – 01-20-23 Weekly Construction Update

January 20, 2023 · District Wide Upgrades 2nd

Work this week: Contractor installed toilet partitions in 4300 restrooms. Framing work is in progress in 6200. Restrooms at 5100 are substantially complete, pending fire alarm and door hardware. Painting has been completed in 4200, adjacent to drinking fountain/eyewash stations.

Download PDF →

4k, 5k, 6k Restroom & Drinking Fountain ADA Upgrades – 01-13-23 Weekly Construction Update

January 13, 2023 · District Wide Upgrades 2nd

Work this week: Contractor has substantially completed 6100 restrooms, and punch walk has been completed. Plumbing fixtures, toilet partitions, and restroom accessories have been hung in 5100. Tile has been installed in 4300 restrooms and concrete patched in 6200 restrooms.

Download PDF →
Older Posts →
  • Search News:

    Search the Cuesta College Bond Website:
  • News Categories

    • Articles
    • Construction Updates
      • 9100 Roofing-HVAC
      • District Wide Asphalt
      • District Wide Upgrades
      • District Wide Upgrades 2nd
      • District-Wide Wayfinding
      • EV Charging Stations
      • Hollister Adobe Stabilization
      • Interim Housing
      • NCC Early Childhood Education Center
      • NCC Parking Lot 10 and Monument Sign
      • North County Campus Center
      • North County Sitework
      • Planning – Aquatic Center
      • Repairs – HVAC/Roofs 1100, 4500, and 4600
      • SLO 1000 Complex Renovations
      • SLO 2000 Complex Renovations
      • SLO Campus Instructional Building
      • SLO Data Center
      • SLO HVAC/Roofs Phase 1
      • SLO HVAC/Roofs Phase 2
      • SLO Switchgear Replacement
      • Technology Upgrades 2nd
      • Technology Upgrades 3rd
      • Upgrades – Aquatic Center
    • Press Releases
    • Uncategorized

Back To Top

Cuesta College Logo
Search the Cuesta College Bond Website: