SLO Campus Center – 09-15-23 Weekly Construction Update
This week, the contractor started forming building perimeter walls on the west 1/3 of the building. Electrical contractor continued installation of under slab electrical conduit. Elevator Pit drain line & backfill was completed. Site utility contractor continued installation of site...
Download PDF →Monthly Project Status Report August 2023 – Issue 92
SLO Campus Center – 09-08-23 Weekly Construction Update
The contractor poured half of the building pad footings and tie-beam footings. Excavation has started on the 2nd half of the building pad footings and tie-beam footings. Elevator pit wall waterproofing was installed. Site utility contractor continued installation of site...
Download PDF →SLO Campus Center – 09-01-23 Weekly Construction Update
The contractor began excavation of the building pad footings and tie-beam footings. Site utility contractor continued installation of site storm drain utility, gas service, and started under slab electrical conduit installation.
Download PDF →SLO Campus Center – 08-25-23 Weekly Construction Update
The contractor poured 7 of 7 structural under slab grade beams. Site utility contractor continued installation of site storm drain utility and site gas main lines.
Download PDF →SLO Campus Center – 08-18-23 Weekly Construction Update
The contractor stripped the elevator pit wall concrete forms. Concrete has been placed in 5 of 7 building grade beams. Site utility contractor continued installation of site storm drain utility and site gas main lines.
Download PDF →NCC Site Signage – 8-11-2023 Weekly Construction Update
Work this week: The contractor retouched the concrete footings and relocated one sign. The last remaining item is the relocation of one traffic sign per district request. Once complete, the final punch will be scheduled.
Download PDF →SLO Campus Center – 08-11-23 Weekly Construction Update
The contractor poured the elevator pit wall concrete as well as two of the seven building grade beams. The site utility contractor continued installing the storm drain and sewer lines.
Download PDF →2400 & 2800 TR Renovation – 08-04-23 Weekly Construction Update
Work this week: The contractor tested & installed 100% of all cable. Building 2400 has been turned over to IT to install patch cables. Final clean-up work is being performed and preliminary punch items are being addressed.
Download PDF →SLO Campus Center – 08-04-23 Weekly Construction Update
Work this week: The contractor finished installing elevator pit wall rebar and concrete formwork for elevator pit walls. Site utility contractor continued installation of site storm drain utility lines and finished underground piping for the site Fire Department Connection (FDC).