Early Childhood Education – 01-22-2021 Weekly Construction Update
Work this week: The revised drainage culvert at the sites north/east corner are being completed. Work on Play yard remains on-going.
Download PDF →NCC Parking Lot 10 & Site Improvements – 01-22-21 Weekly Construction Update
Work this week: New concrete was poured at the front of the Campus Center. Additional concrete was poured at the front drive aisle entrance off Buena Vista Drive.
Download PDF →NCC Parking Lot 10 & Site Improvements – 01-15-21 Weekly Construction Update
Work this week: New concrete was poured at the front of the Campus Center. New curb, gutter, and accessible pathways were also poured at the entrance to Parking Lot 11.
Download PDF →NCC Parking Lot 10 & Site Improvements – 01-08-21 Weekly Construction Update
Work this week: The first lift of asphalt was placed in Parking Lot 10. Additional concrete was poured around the Parking Lot.
Download PDF →Early Childhood Education – 12-18-2020 Weekly Construction Update
Work this week: The lobby quartz counters were installed, concrete at the front & exterior was being completed. The gates and steel fences are mid-way to having their coats of paint completed. ECE is scheduled to be substantially complete on...
Download PDF →Buildings 4000-7000 Wireless and TR Upgrades – 12-18-20 Weekly Construction Update
Work this week: Contractor installed new cable and raceways in Buildings 4200, 4400, 4600 and pulled new cable along the hallway of Building 4300. New data cabinets have been installed in building 6100 and 6300 as they work to complete...
Download PDF →Asphalt Resurfacing Phase II – 12-18-20 Weekly Construction Update
Work this week: General contractor installed an asphalt path at Building 7500. The asphalt walkway at Parking Lot 6 was completed. New striping was added to the 5000 Buildings loading dock. Striping work continued at Parking Lot 2.
Download PDF →NCC Parking Lot 10 & Site Improvements – 12-18-20 Weekly Construction Update
Work this week: Concrete was poured in the bus drop-off area, curbs were poured on the east end of Parking Lot 10, and light pole bases around the site were put into place.
Download PDF →Early Childhood Education – 12-11-2020 Weekly Construction Update
Work this week: New entrance mats at the lobby and other entrances are being installed. The concrete at the front was being renovated & the mock up for the new decomposed granite playground sitting area was approved and is ready...
Download PDF →NCC Parking Lot 10 & Site Improvements – 12-11-20 Weekly Construction Update
Work this week: Rough grading, and formwork remains ongoing. Additional gutters were poured.
Download PDF →