2400 & 2800 TR Renovation – 08-04-23 Weekly Construction Update
Work this week: The contractor tested & installed 100% of all cable. Building 2400 has been turned over to IT to install patch cables. Final clean-up work is being performed and preliminary punch items are being addressed.
Download PDF →2400 & 2800 TR Renovation – 07-28-23 Weekly Construction Update
Work this week: The contractor has tested 70% of all fiberoptic cables pulled into N2400. Labeling is 99% complete, and there are 120 remaining cables to be landed in the IDF room.
Download PDF →2400 & 2800 TR Renovation – 07-21-23 Weekly Construction Update
Work this week: The contractor has made the final underground pulls, and are currently making terminations and testing fiberoptic cables.
Download PDF →2400 & 2800 TR Renovation – 07-07-23 Weekly Construction Update
Work this week: The contractor pulled all runs and made terminations at Building 2800, and testing has been completed. Terminations at Building 2400 are currently in progress.
Download PDF →2400 & 2800 TR Renovation – 06-30-23 Weekly Construction Update
Work this week: The contractor removed all existing cable and continues to pull new cable. Terminations are expected to take place next week.
Download PDF →March Monthly Project Updates
Monthly status update.
Download PDF →December Monthly Project Updates
Monthly status update.
Download PDF →COE Fiber Run – 12-9-22 Weekly Construction Update
Work this week: Contractor pulled fiber to COE Teleplex building. During patch in, it was discovered that an existing patch cable has failed. Taft Electric has made a temporary fix and will order a new patch cable. Please note that...
Download PDF →COE Fiber Run – 10-26-22 Weekly Construction Update
Work this week: Contractor completed directional boring and installed all underground conduits and vaults. All fiberoptic cable has been received. Updated schedule pending.
Download PDF →September Monthly Project Updates
Monthly status update.
Download PDF →