SLO 6100, 6300, and 7100 Roofing and HVAC – 05-13-22 Weekly Construction Update
Work this week: Condensate and gas lines were connected to the rooftop packaged HVAC unit serving classroom 6301.
Download PDF →Restroom/Drinking Fountain ADA Upgrades – 05-06-22 Weekly Construction Update
Work this week: Contractor completed tile installation in Building 4000 restrooms. Construction team poured concrete at Building 7100 and 4000. Plumbing contractor began installation of drinking fountains at the Tennis Court area.
Download PDF →SLO 6100, 6300, and 7100 Roofing and HVAC – 05-06-22 Weekly Construction Update
Work this week: The rooftop HVAC unit serving classroom 6301 was delivered and set on the roof.
Download PDF →April Monthly Project Update – SLO Campus Police Department Renovation
Monthly status update on SLO Campus Police Department Renovation project.
Download PDF →April Monthly Project Update – SLO Campus RR & Drinking Fountain ADA Upgrades
Monthly status update on SLO Campus Restrooms/Drinking Fountain ADA Upgrades projects.
Download PDF →9100 Roofing and HVAC – 04-22-22 Weekly Construction Update
Work this week: Contractor completed Test and Balance work. Punchlist work is in progress. The project is now substantially complete.
Download PDF →Restroom/Drinking Fountain ADA Upgrades – 04-15-22 Weekly Construction Update
Work this week: Contractor completed the demolition in Building 7100. Construction team installed drywall in Building 4000. Building 4000 has been prepped to receive tile.
Download PDF →9100 Roofing and HVAC – 04-15-22 Weekly Construction Update
Work this week: Contractor completed the plenum and duct work on the vehicle exhaust fan and electrical connections to all new HVAC equipment.
Download PDF →9100 Roofing and HVAC – 04-08-22 Weekly Construction Update
Work this week: Contractor installed new parapet cleats and coping, as well as a new sheet metal cap on the exhaust fan curb. Downspout installation work remains ongoing.
Download PDF →Restroom/Drinking Fountain ADA Upgrades – 04-08-22 Weekly Construction Update
Work this week: Contractor completed framing and MEP rough in at Building 4000 and 1400 (gymnasium). Demolition is ongoing in Building 7100.
Download PDF →