4k, 5k, 6k Restroom & Drinking Fountain ADA Upgrades – 05-12-23 Weekly Construction Update
Work this week: The contractor completed installation of plumbing fixtures, restroom accessories and toilet partitions in Building 6200 restrooms. Access hatches and lighting fixtures are scheduled to be installed next week.
Download PDF →4k, 5k, 6k Restroom & Drinking Fountain ADA Upgrades – 05-05-23 Weekly Construction Update
Work this week: The contractor completed tile floor installation. Plumbing fixtures are currently being installed.
Download PDF →April Monthly Project Updates
Monthly Status Update.
Download PDF →4k, 5k, 6k Restroom & Drinking Fountain ADA Upgrades – 04-28-23 Weekly Construction Update
Work this week: The contractor finished installing wall tile and floor sealer in the 6200 restrooms. Grout and floor tile will begin on Monday May 1, 2023.
Download PDF →4k, 5k, 6k Restroom & Drinking Fountain ADA Upgrades – 04-14-23 Weekly Construction Update
Work this week: Contractor hung, taped and painted lids in 6200 men’s and women’s restrooms. New wall at drinking fountain alcove has been insulated and began floating walls are in preparation for tile.
Download PDF →SLO Electrical Building Switchgear Replacement – 04-07-23 Weekly Construction Update
Work this week: Contractor has installed roofing underlayment and rake supports. Pending approval of rake installation. Plaster installation work has been completed, and a base coat of paint has been applied.
Download PDF →4k, 5k, 6k Restroom & Drinking Fountain ADA Upgrades – 04-07-23 Weekly Construction Update
Work this week: Contractor has completed fire caulking overhead bracing and installed lath at Building 6200. Lids have also been hung in the men’s restroom.
Download PDF →March Monthly Project Updates
Monthly status update.
Download PDF →Chiller Replacement – 03-31-23
Work this week: Contractor has installed all three chillers. Electrical cut over has been completed. Manufacturer is scheduled to begin start up this week.
Download PDF →SLO Electrical Building Switchgear Replacement – 03-31-23 Weekly Construction Update
Work this week: Contractor has completed framing and plastering. The roofing underlayment is in place, and ready for tile roofing to begin.
Download PDF →