4k, 5k, 6k Restroom & Drinking Fountain ADA Upgrades – 01-20-23 Weekly Construction Update
Work this week: Contractor installed toilet partitions in 4300 restrooms. Framing work is in progress in 6200. Restrooms at 5100 are substantially complete, pending fire alarm and door hardware. Painting has been completed in 4200, adjacent to drinking fountain/eyewash stations.
Download PDF →4k, 5k, 6k Restroom & Drinking Fountain ADA Upgrades – 01-13-23 Weekly Construction Update
Work this week: Contractor has substantially completed 6100 restrooms, and punch walk has been completed. Plumbing fixtures, toilet partitions, and restroom accessories have been hung in 5100. Tile has been installed in 4300 restrooms and concrete patched in 6200 restrooms.
Download PDF →4k, 5k, 6k Restroom & Drinking Fountain ADA Upgrades – 01-06-23 Weekly Construction Update
Work this week: Contractor has substantially completed 6100 restrooms, and punch walk has been completed. Tile is now complete at 5100, and drywall/sheetrock has been hung in 4300. Ceilings have been painted and floors floated. Demolition at 6200, is complete....
Download PDF →December Monthly Project Updates
Monthly status update.
Download PDF →SLO Electrical Building Switchgear Replacement – 12-23-22 Weekly Construction Update
Work this week: Contractor completed block walls and installed anchor bolts for roof framing which began this week.
Download PDF →4k, 5k, 6k Restroom & Drinking Fountain ADA Upgrades – 12-23-22 Weekly Construction Update
Work this week: Contractor has substantially completed 6100 restrooms and is preparing for punch walk next week. Tile is in progress at 5100, and drywall/sheetrock has been hung in 4300.
Download PDF →SLO Electrical Building Switchgear Replacement – 12-16-22 Weekly Construction Update
Work this week: Contractor demolished a portion of the north facing wall which did not have adequate grout penetration. That portion has been reconstructed and framing is scheduled to begin on Monday. Temporary transformer and pad have also been set...
Download PDF →4k, 5k, 6k Restroom & Drinking Fountain ADA Upgrades – 12-16-22 Weekly Construction Update
Work this week: Contractor has completed tile in 6100 restrooms and plumbing fixtures/partitions are being installed. Framing in 4300 is substantially complete and above ground plumbing/electrical is in progress. The tile crew also started floating floors in 5100 today.
Download PDF →SLO Electrical Building Switchgear Replacement – 12-9-22 Weekly Construction Update
Work this week: Contractor poured concrete slab. However, core samples revealed inadequate grout penetration of block cells. Contractor has been instructed by structural engineer to demo a portion of the north facing wall.
Download PDF →COE Fiber Run – 12-9-22 Weekly Construction Update
Work this week: Contractor pulled fiber to COE Teleplex building. During patch in, it was discovered that an existing patch cable has failed. Taft Electric has made a temporary fix and will order a new patch cable. Please note that...
Download PDF →