January 2020 Monthly Project Update
Monthly status update on all existing Measure L projects.
Download PDF →Technology Upgrades Project – Fiber Star – 10-25-19 Weekly Construction Update
Work this week: The general contractor completed the overhead conduit run in Building 9100...
Download PDF →Technology Upgrades Project – 2000 Complex – 10-18-19 Weekly Construction Update
Work this week: The general contractor completed the installation of the exterior conduit and box at Building 2000...
Download PDF →Technology Upgrades Project – 2000 Complex – 10-11-19 Weekly Construction Update
Work this week: The general contractor completed the underground electrical work from the Data Center vaults to Building 2200...
Download PDF →September 2019 Monthly Project Update
Monthly status update on all existing Measure L projects.
Download PDF →August 2019 Monthly Project Update
Monthly status update on all existing Measure L projects.
Download PDF →2000 Complex Renovations Project – 08-16-19 Weekly Construction Update
Work This Week: Construction crews have completed the Wireless and TR Upgrades Project...
Download PDF →2000 Complex Renovations Project – 07-19-19 Weekly Construction Update
Work This Week: Construction crews continued to work in the 2000 Complex, which included installing racks in the new cabinet in Building 2300 and working on exterior access points in Buildings 2100, 2200, and 2400...
Download PDF →2000 Complex Renovations Project – 07-12-19 Weekly Construction Update
Work This Week: Construction crews continued to work in Building 2300 with the installation of racks in the new cabinet...
Download PDF →2000 Complex Renovations Project – 07-21-19 Weekly Construction Update
Work This Week: Construction crews finished the installation of Wireless Access Points in Building 2400 and patched IDF in the projector room...
Download PDF →