Category: Repairs – HVAC/Roofs

October 2020 Monthly Project Update

October 31, 2020 · Construction Updates, District Wide Asphalt, NCC Early Childhood Education Center, North County Sitework, Repairs – HVAC/Roofs

Monthly status update on all existing Measure L projects.

Download PDF →

September 2020 Monthly Project Update

September 30, 2020 · District Wide Asphalt, NCC Early Childhood Education Center, NCC Parking Lot 10 and Monument Sign, North County Campus Center, North County Sitework, Repairs – HVAC/Roofs, SLO 2000 Complex Renovations, SLO Roofing-HVAC

Monthly status update on all existing Measure L projects.

Download PDF →

January 2020 Monthly Project Update

February 1, 2020 · Construction Updates, EV Charging Stations, NCC Early Childhood Education Center, Repairs – HVAC/Roofs, SLO 2000 Complex Renovations, Technology Upgrades 2nd

Monthly status update on all existing Measure L projects.

Download PDF →

November 2019 Monthly Project Update

December 1, 2019 · Construction Updates, EV Charging Stations, NCC Early Childhood Education Center, Repairs – HVAC/Roofs, SLO 2000 Complex Renovations, SLO Data Center

Monthly status update on all existing Measure L projects.

Download PDF →

July 2019 Monthly Project Update

August 1, 2019 · Construction Updates, NCC Early Childhood Education Center, Repairs – HVAC/Roofs, SLO 1000 Complex Renovations, SLO Data Center, Upgrades - Aquatic Center

Monthly status update on all existing Measure L projects.

Download PDF →

June 2019 Monthly Project Update

July 1, 2019 · Construction Updates, NCC Early Childhood Education Center, Repairs – HVAC/Roofs, SLO 1000 Complex Renovations, SLO Data Center, Upgrades - Aquatic Center

Monthly status update on all existing Measure L projects.

Download PDF →

1000 Complex Roof/HVAC Replacement – 10-05-18 Weekly Construction Update

October 5, 2018 · Construction Updates, Repairs – HVAC/Roofs, SLO 1000 Complex Renovations

Controls for the mechanical equipment is complete, and the final electrical connections to mechanical equipment was complete this week. Condensate lines were hooked up to condensers and charged. Scheduled start-up is 10/9/18.

Download PDF →

1000 Complex Roof/HVAC Replacement – 9-29-18 Weekly Construction Update

September 29, 2018 · Construction Updates, Repairs – HVAC/Roofs, SLO 1000 Complex Renovations

Installation of the controls for the mechanical equipment is ongoing, and the team began installing T-stats in buildings 1000 and 1300. Startup is scheduled for 10/9/18. The temporary fencing has been removed from around buildings 1000 and 1300.

Download PDF →

1000 Complex Roof/HVAC Replacement – 09-21-18 Weekly Construction Update

September 21, 2018 · Construction Updates, Repairs – HVAC/Roofs, SLO 1000 Complex Renovations

Work this week: The contractors completed the install of the parapet cap, and the mechanical contractor completed the install of the duct work on the roof of building 1000...

Download PDF →

1000 Complex Roof/HVAC Replacement – 09-14-18 Weekly Construction Update

September 14, 2018 · Construction Updates, Repairs – HVAC/Roofs, SLO 1000 Complex Renovations

Work this week: Began installing the parapet cap on building 1000...

Download PDF →
Older Posts →
  • Search News:

    Search the Cuesta College Bond Website:
  • News Categories

    • Articles
    • Construction Updates
      • District Wide Asphalt
      • District Wide Upgrades
      • EV Charging Stations
      • Hollister Adobe Stabilization
      • Interim Housing
      • NCC Early Childhood Education Center
      • NCC Parking Lot 10 and Monument Sign
      • North County Campus Center
      • North County Sitework
      • Planning – Aquatic Center
      • Repairs – HVAC/Roofs
      • SLO 1000 Complex Renovations
      • SLO 2000 Complex Renovations
      • SLO Campus Instructional Building
      • SLO Data Center
      • SLO Roofing-HVAC