May Monthly Project Updates
Monthly Status Update.
Download PDF →April Monthly Project Updates
Monthly Status Update.
Download PDF →SLO Electrical Building Switchgear Replacement – 04-07-23 Weekly Construction Update
Work this week: Contractor has installed roofing underlayment and rake supports. Pending approval of rake installation. Plaster installation work has been completed, and a base coat of paint has been applied.
Download PDF →March Monthly Project Updates
Monthly status update.
Download PDF →SLO Electrical Building Switchgear Replacement – 03-31-23 Weekly Construction Update
Work this week: Contractor has completed framing and plastering. The roofing underlayment is in place, and ready for tile roofing to begin.
Download PDF →SLO Electrical Building Switchgear Replacement – 03-31-23 Weekly Construction Update
Work this week: Contractor has completed framing and plastering. The roofing underlayment is in place, and ready for tile roofing to begin.
Download PDF →SLO Electrical Building Switchgear Replacement – 02-17-23 Weekly Construction Update
Work this week: Roof framing is on hold pending arrival of new 4x6” nailers, which should be here this week. NCM is currently laying base in preparation for concrete flatwork which will be poured this week.
Download PDF →January Monthly Project Updates
Monthly status update.
Download PDF →December Monthly Project Updates
Monthly status update.
Download PDF →SLO Electrical Building Switchgear Replacement – 12-23-22 Weekly Construction Update
Work this week: Contractor completed block walls and installed anchor bolts for roof framing which began this week.
Download PDF →