SLO Electrical Building Switchgear Replacement – 12-16-22 Weekly Construction Update
Work this week: Contractor demolished a portion of the north facing wall which did not have adequate grout penetration. That portion has been reconstructed and framing is scheduled to begin on Monday. Temporary transformer and pad have also been set...
Download PDF →SLO Electrical Building Switchgear Replacement – 12-9-22 Weekly Construction Update
Work this week: Contractor poured concrete slab. However, core samples revealed inadequate grout penetration of block cells. Contractor has been instructed by structural engineer to demo a portion of the north facing wall.
Download PDF →SLO Electrical Building Switchgear Replacement – 12-2-22 Weekly Construction Update
Work this week: Contractor grouted previously installed courses of block and continued erecting remaining courses. Mixer is on site today to pour grout in the last courses of block.
Download PDF →November Monthly Project Updates
Monthly status update.
Download PDF →SLO Electrical Building Switchgear Replacement – 11-25-22 Weekly Construction Update
Work this week: Contractor continued erecting block walls at 6300.
Download PDF →SLO Electrical Building Switchgear Replacement – 11-18-22 Weekly Construction Update
Work this week: Contractor began erecting block walls and installed double door frame. Trenches were backfilled at walkways and asphalt paving work has been completed.
Download PDF →SLO Electrical Building Switchgear Replacement – 11-11-22 Weekly Construction Update
Work this week: Contractor installed electrical vaults and began installing the associated conduits. They have also started backfilling where a section of the existing sewer was replaced.
Download PDF →SLO Electrical Building Switchgear Replacement – 11-4-22 Weekly Construction Update
Work this week: Contractor performed trenching work in preparation to run conduits from switchgear pad at 6300 to UG conduits located at 6200.
Download PDF →SLO Electrical Building Switchgear Replacement – 10-26-22 Weekly Construction Update
Work this week: Contractor poured concrete footings at 6300 and cut CMU block in preparation to lay first courses. Construction team is prepared to lay first block courses so they can start preparing to pour the concrete slab.
Download PDF →September Monthly Project Updates
Monthly status update.
Download PDF →