Monthly Project Status Report July 2023 – Issue 91
Monthly Status Update.
Download PDF →SLO Campus Center – 07-28-23 Weekly Construction Update
Work this week: The contractor finished installing building grade beam rebar. Grade Beam concrete is scheduled for next week. Site utility contractor started installation of site storm drain lines. Electrical & Telecommunication conduit continue to be installed into the building...
Download PDF →2400 & 2800 TR Renovation – 07-28-23 Weekly Construction Update
Work this week: The contractor has tested 70% of all fiberoptic cables pulled into N2400. Labeling is 99% complete, and there are 120 remaining cables to be landed in the IDF room.
Download PDF →2400 & 2800 TR Renovation – 07-21-23 Weekly Construction Update
Work this week: The contractor has made the final underground pulls, and are currently making terminations and testing fiberoptic cables.
Download PDF →SLO Campus Center – 07-14-23 Weekly Construction Update
Work this week: This week, the contractor has started excavating the building grade beams, installed the building fire riser piping, and brought the 12kv high voltage electrical conduit into the building perimeter. Concrete form work and rebar installation continues on...
Download PDF →2400 & 2800 TR Renovation – 07-07-23 Weekly Construction Update
Work this week: The contractor pulled all runs and made terminations at Building 2800, and testing has been completed. Terminations at Building 2400 are currently in progress.
Download PDF →SLO Campus Center – 07-07-23 Weekly Construction Update
Work this week: The contractor laid and compacted engineered fill (base) over the entire building pad and marked the locations of the building grade beams. Excavation for building grade beams will begin next week. Concrete form work and rebar installation...
Download PDF →2400 & 2800 TR Renovation – 06-30-23 Weekly Construction Update
Work this week: The contractor removed all existing cable and continues to pull new cable. Terminations are expected to take place next week.
Download PDF →SLO Campus Center – 06-30-23 Weekly Construction Update
Work this week: The contractor continued backfilling the under-slab plumbing trenches. Elevator pit rebar was installed; pit floor and footings have been poured. Contractor will begin forming elevator pit walls next week. Trenching and installation of site domestic water and...
Download PDF →June Monthly Project Updates
Monthly Status Update.
Download PDF →