Buildings 4000-7000 Wireless and TR Upgrades – 12-18-20 Weekly Construction Update
Work this week: Contractor installed new cable and raceways in Buildings 4200, 4400, 4600 and pulled new cable along the hallway of Building 4300. New data cabinets have been installed in building 6100 and 6300 as they work to complete...
Download PDF →Asphalt Resurfacing Phase II – 12-18-20 Weekly Construction Update
Work this week: General contractor installed an asphalt path at Building 7500. The asphalt walkway at Parking Lot 6 was completed. New striping was added to the 5000 Buildings loading dock. Striping work continued at Parking Lot 2.
Download PDF →NCC Parking Lot 10 & Site Improvements – 12-18-20 Weekly Construction Update
Work this week: Concrete was poured in the bus drop-off area, curbs were poured on the east end of Parking Lot 10, and light pole bases around the site were put into place.
Download PDF →Early Childhood Education – 12-11-2020 Weekly Construction Update
Work this week: New entrance mats at the lobby and other entrances are being installed. The concrete at the front was being renovated & the mock up for the new decomposed granite playground sitting area was approved and is ready...
Download PDF →NCC Parking Lot 10 & Site Improvements – 12-11-20 Weekly Construction Update
Work this week: Rough grading, and formwork remains ongoing. Additional gutters were poured.
Download PDF →Buildings 4000-7000 Wireless and TR Upgrades – 12-04-20 Weekly Construction Update
Work this week: Contractor is working on Building 6100 and 6300 removing existing network cables and installing new Cat6A cable, along with new raceways and outlets. Work in Building 5100 & 5300 also began.
Download PDF →Asphalt Resurfacing Phase II – 12-04-20 Weekly Construction Update
Work this week: General contractor paved Parking Lot 1 and continued paving Parking Lot 2. Demo began on driveway concrete at Parking Lot 1. Seal coat applied to the basketball court.
Download PDF →NCC Parking Lot 10 & Site Improvements – 12-04-20 Weekly Construction Update
Work this week: Aggregate base compaction continued, curb and gutter as well as flatwork were put into place, CMU monument signage was grouted, and the existing parking ticket dispenser was removed to be replaced with a new unit in the...
Download PDF →November 2020 Monthly Project Update
Monthly status update on all existing Measure L projects.
Download PDF →NCC Parking Lot 10 & Site Improvements – 11-27-20 Weekly Construction Update
Work this week: Aggregate base compaction continued in traffic areas, and CMU entrance walls were constructed at the entrance of Parking Lot 10.
Download PDF →