4k, 5k, 6k Restroom & Drinking Fountain ADA Upgrades – 12-23-22 Weekly Construction Update
Work this week: Contractor has substantially completed 6100 restrooms and is preparing for punch walk next week. Tile is in progress at 5100, and drywall/sheetrock has been hung in 4300.
Download PDF →SLO Electrical Building Switchgear Replacement – 12-16-22 Weekly Construction Update
Work this week: Contractor demolished a portion of the north facing wall which did not have adequate grout penetration. That portion has been reconstructed and framing is scheduled to begin on Monday. Temporary transformer and pad have also been set...
Download PDF →4k, 5k, 6k Restroom & Drinking Fountain ADA Upgrades – 12-16-22 Weekly Construction Update
Work this week: Contractor has completed tile in 6100 restrooms and plumbing fixtures/partitions are being installed. Framing in 4300 is substantially complete and above ground plumbing/electrical is in progress. The tile crew also started floating floors in 5100 today.
Download PDF →SLO Electrical Building Switchgear Replacement – 12-9-22 Weekly Construction Update
Work this week: Contractor poured concrete slab. However, core samples revealed inadequate grout penetration of block cells. Contractor has been instructed by structural engineer to demo a portion of the north facing wall.
Download PDF →COE Fiber Run – 12-9-22 Weekly Construction Update
Work this week: Contractor pulled fiber to COE Teleplex building. During patch in, it was discovered that an existing patch cable has failed. Taft Electric has made a temporary fix and will order a new patch cable. Please note that...
Download PDF →4k, 5k, 6k Restroom & Drinking Fountain ADA Upgrades – 12-9-22 Weekly Construction Update
Work this week: Restrooms at 4100 have been completed and punched. Fire alarm test and punch list items are still pending. Contractor is currently framing in 4300 and tile is being installed in 6100.
Download PDF →SLO Electrical Building Switchgear Replacement – 12-2-22 Weekly Construction Update
Work this week: Contractor grouted previously installed courses of block and continued erecting remaining courses. Mixer is on site today to pour grout in the last courses of block.
Download PDF →Chiller Replacement – 12-2-22
Work this week: Contractor began replacing existing pumps. One chiller unit was removed/replaced. Chiller yard is currently running on a mobile chiller, so there are no interruptions at this time.
Download PDF →4k, 5k, 6k Restroom & Drinking Fountain ADA Upgrades – 12-2-22 Weekly Construction Update
Work this week: Contractor installed fire alarm in building 4100 and began clearing conduit pathways to 4200. Underground plumbing and concrete patch has been completed in building 4300 and tile crew has installed tile at exterior drinking fountains.
Download PDF →November Monthly Project Updates
Monthly status update.