4k, 5k, 6k Restroom & Drinking Fountain ADA Upgrades – 12-9-22 Weekly Construction Update
Work this week: Restrooms at 4100 have been completed and punched. Fire alarm test and punch list items are still pending. Contractor is currently framing in 4300 and tile is being installed in 6100.
Download PDF →SLO Electrical Building Switchgear Replacement – 12-2-22 Weekly Construction Update
Work this week: Contractor grouted previously installed courses of block and continued erecting remaining courses. Mixer is on site today to pour grout in the last courses of block.
Download PDF →Chiller Replacement – 12-2-22
Work this week: Contractor began replacing existing pumps. One chiller unit was removed/replaced. Chiller yard is currently running on a mobile chiller, so there are no interruptions at this time.
Download PDF →4k, 5k, 6k Restroom & Drinking Fountain ADA Upgrades – 12-2-22 Weekly Construction Update
Work this week: Contractor installed fire alarm in building 4100 and began clearing conduit pathways to 4200. Underground plumbing and concrete patch has been completed in building 4300 and tile crew has installed tile at exterior drinking fountains.
Download PDF →November Monthly Project Updates
Monthly status update.
Download PDF →SLO Electrical Building Switchgear Replacement – 11-25-22 Weekly Construction Update
Work this week: Contractor continued erecting block walls at 6300.
Download PDF →4k, 5k, 6k Restroom & Drinking Fountain ADA Upgrades – 11-25-22 Weekly Construction Update
Work this week: Contractor continued installation of lath and began floating floors in building 6100. Underground plumbing is ongoing in building 4300.
Download PDF →SLO Electrical Building Switchgear Replacement – 11-18-22 Weekly Construction Update
Work this week: Contractor began erecting block walls and installed double door frame. Trenches were backfilled at walkways and asphalt paving work has been completed.
Download PDF →4k, 5k, 6k Restroom & Drinking Fountain ADA Upgrades – 11-18-22 Weekly Construction Update
Work this week: Contractor hung drywall lids and installed lath system at Building 6100. Plumbing fixtures have been installed in 4100 and toilet partitions are in progress. Demolition work at Building 4300 has been completed and underground plumbing work remains...
Download PDF →SLO Electrical Building Switchgear Replacement – 11-11-22 Weekly Construction Update
Work this week: Contractor installed electrical vaults and began installing the associated conduits. They have also started backfilling where a section of the existing sewer was replaced.
Download PDF →