SLO Instructional Building – 04-07-17 Weekly Construction Update
Work this week: Framing of the second floor interior walls has continued...
Download PDF →March 2017 Monthly Project Update
Monthly status update on all existing Measure L projects.
Download PDF →SLO Instructional Building – 03-31-17 Weekly Construction Update
Work this week: The electricians began the wall rough-in on the second floor and installing their equipment racks on the roof...
Download PDF →SLO Instructional Building – 03-24-17 Weekly Construction Update
Work this week: The metal framing contractor was installing backing in areas previously identified...
Download PDF →SLO Instructional Building – 03-17-17 Weekly Construction Update
Work this week: The interior stairwell walls were framed...
Download PDF →SLO Instructional Building – 03-10-17 Weekly Construction Update
Work this week: The roofing contractor began to install the single ply roofing, the second floor restrooms walls have started to be framed, and the exterior stair was installed on the east side of the building...
Download PDF →SLO Instructional Building – 03-03-17 Weekly Construction Update
Work this week: The fire sprinkler rough-in was completed on the first floor...
Download PDF →February 2017 Monthly Project Updates
Monthly status update on all existing Measure L projects.
Download PDF →SLO Instructional Building – 02-24-17 Weekly Construction Update
Work this week: The fire sprinkler rough-in is 90% complete on the first floor...
Download PDF →SLO Instructional Building – 02-03-17 Weekly Construction Update
Work this week: The metal framer began to place interior walls on the first floor...
Download PDF →