January 2017 Monthly Project Updates
Monthly status update on all existing Measure L projects.
Download PDF →SLO Instructional Building – 01-27-17 Weekly Construction Update
Work this week: The metal framing contractor continued their placement of the second floor exterior infill...
Download PDF →SLO Instructional Building – 01-13-17 Weekly Construction Update
Work this week: The concrete contractor placed the last portion of the second floor deck...
Download PDF →SLO Instructional Building – 01-20-17 Weekly Construction Update
Work this week: The metal framing contractor began to weld the second floor track to the tube steel frames and continued to frame the exterior infills...
Download PDF →SLO Instructional Building – 01-06-17 Weekly Construction Update
Work this week: The concrete contractor has placed roughly 65% of the second floor slab...
Download PDF →December 2016 Monthly Project Update
Monthly status update on all existing Measure L projects.
Download PDF →SLO Instructional Building – 12-23-16 Weekly Construction Update
Work this week: Rebar has been installed on the second floor deck, and the lighting in the cantilevered slab has been roughed in...
Download PDF →SLO Instructional Building – 12-16-16 Weekly Construction Update
Work this week: The mansard decking has been completed...
Download PDF →SLO Instructional Building – 12-09-16 Weekly Construction Update
Work this week: The mansard decking is currently approximately 90% complete...
Download PDF →SLO Instructional Building – 12-02-16 Weekly Construction Update
Work this week: The mansard decking is approximately 25% complete...