November 2016 Monthly Project Update
December 1, 2016 · Construction Updates, North County Campus Center, SLO Campus Instructional Building
Monthly status update on all existing Measure L projects.
Download PDF →SLO Instructional Building – 11-25-16 Weekly Construction Update
November 25, 2016 · Construction Updates, SLO Campus Instructional Building
Work this week: The mansard decking is roughly 25% complete...
Download PDF →SLO Instructional Building – 11-18-16 Weekly Construction Update
November 18, 2016 · Construction Updates, SLO Campus Instructional Building
Work this week: The placement of the mansard decking has begun...
Download PDF →SLO Instructional Building – 11-11-16 Weekly Construction Update
November 11, 2016 · Construction Updates, SLO Campus Instructional Building
Work this week: The second floor decking was completed and roof decking is nearing completion...
Download PDF →SLO Instructional Building – 11-04-16 Weekly Construction Update
November 4, 2016 · Construction Updates, SLO Campus Instructional Building
Work this week: All structural steel has been erected...
Download PDF →October 2016 Monthly Project Update
November 1, 2016 · Construction Updates, North County Campus Center, SLO Campus Instructional Building
Monthly status update on all existing Measure L projects.
Download PDF →SLO Instructional Building – 10-28-16 Weekly Construction Update
October 28, 2016 · Construction Updates, SLO Campus Instructional Building
Work this week: The structural steel is close to completion...
Download PDF →SLO Instructional Building – 10-21-16 Weekly Construction Update
October 21, 2016 · Construction Updates, SLO Campus Instructional Building
Work this week: Approximately 90% of the structural steel is on site and has been erected...
Download PDF →SLO Instructional Building – 10-14-16 Weekly Construction Update
October 14, 2016 · Construction Updates, SLO Campus Instructional Building
Work this week: Steel erection continues and the steel erection is approximately 75% complete...
Download PDF →September 2016 Monthly Project Update
October 10, 2016 · North County Campus Center, SLO Campus Instructional Building
Monthly status update on all existing Measure L projects.
Download PDF →