SLO Instructional Building – 06-02-17 Weekly Construction Update
Work this week: The metal framing is complete on the first floor, and the first and second layer of drywall has been set in multiple classrooms...
Download PDF →May 2017 Monthly Project Update
Monthly status update on all existing Measure L projects.
Download PDF →SLO Instructional Building – 05-26-17 Weekly Construction Update
Work this week: The elevator install continues to progress...
Download PDF →SLO Instructional Building – 05-19-17 Weekly Construction Update
Work this week: The elevator arrived and the installation has begun...
Download PDF →SLO Instructional Building – 05-12-17 Weekly Construction Update
Work this week: Framing and drywall installation began on the second floor...
Download PDF →SLO Instructional Building – 05-05-17 Weekly Construction Update
Work this week: The exterior columns have been framed and sheathing of these columns has begun...
Download PDF →April 2017 Monthly Project Update
Monthly status update on all existing Measure L projects.
Download PDF →SLO Instructional Building – 04-28-17 Weekly Construction Update
Work this week: The building’s fire line was installed and has passed inspection...
Download PDF →SLO Instructional Building – 04-21-17 Weekly Construction Update
Work this week: The window framing contractor has begun to install window and door frames...
Download PDF →SLO Instructional Building – 04-14-17 Weekly Construction Update
Work this week: The electrical contractor has installed and connected the switchgear in the building...