North County Campus Center – 10-06-17 Weekly Construction Update
Work this week: Contractors continue the installation of the drywall, insulation, acoustical ceilings, HVAC, electrical, painting, communications, data and fire protection on the 1st and 2nd floors...
Download PDF →September 2017 Monthly Project Update
Monthly status update on all existing Measure L projects.
Download PDF →North County Campus Center – 09-28-17 Weekly Construction Update
Work this week: Contractors continue the installation of the drywall, insulation, HVAC, electrical, painting, communications, Data and Fire Protection on the 1st and 2nd floors...
Download PDF →North County Campus Center – 09-22-17 Weekly Construction Update
Work this week: Drywall installation, tape, texture, and finish continues on the 1st and 2nd floor with interior paint following along...
Download PDF →North County Campus Center – 09-15-17 Weekly Construction Update
Work this week: Drywall installation has started at the computer lab skylight opening and continues throughout the building...
Download PDF →North County Campus Center – 09-08-17 Weekly Construction Update
Work this week: Plaster, drywall, interior and exterior paint, and acoustical ceiling installation continue to progress...
Download PDF →North County Campus Center – 09-01-17 Weekly Construction Update
Work this week: Drywall, paint, and acoustical ceiling installation continue to progress and the K-13 spray acoustical insulation was complete in the in the main entry and the cafeteria...
Download PDF →August 2017 Monthly Project Update
Monthly status update on all existing Measure L projects.
Download PDF →North County Campus Center – 08-25-17 Weekly Construction Update
Work this week: The standing-seam-metal roof at the high roof is complete...
Download PDF →North County Campus Center – 08-18-17 Weekly Construction Update
Work this week: Installation of the standing seam roof at the high roof area began this week and is near completion...
Download PDF →