North County Campus Center – 01-19-18 Weekly Construction Update
Work this week: Plumbing, HVAC, electrical, acoustical plaster, communications, fire protection, drywall, glazing, tile, doors & hardware, painting, kitchen, and ceiling contractors continue to move forward on both floors of the building...
Download PDF →North County Campus Center – 01-12-18 Weekly Construction Update
Work this week: The plumbing, HVAC, electrical, acoustical plaster, communications, fire protection, drywall, glazing, tile, doors & hardware, painting, kitchen, and ceiling contractors continue to move forward on both floors of the building.
Download PDF →North County Campus Center – 01-05-18 Weekly Construction Update
Work this week: Installation of various ceilings throughout the building is progressing...
Download PDF →December 2017 Monthly Project Update
Monthly status update on all existing Measure L projects.
Download PDF →North County Campus Center – 12-22-17 Weekly Construction Update
Work this week: The HVAC system was started up in order for the building to be conditioned...
Download PDF →North County Campus Center – 12-15-17 Weekly Construction Update
Work this week: The skylight installation is complete, and the torsion spring ceiling grid at the high ceiling continues...
Download PDF →North County Campus Center – 12-08-17 Weekly Construction Update
Work this week: The installation of the high ceiling continues, the skylight installation is near completion, and the curtain wall system is moving forward...
Download PDF →November 2017 Monthly Project Update
Monthly status update on all existing Measure L projects.
Download PDF →North County Campus Center – 12-01-17 Weekly Construction Update
Work this week: A fair weather forecast allowed the skylight installation to continue, and the concrete at terrace deck was placed...
Download PDF →North County Campus Center – 11-24-17 Weekly Construction Update
Work this week: Many of the trade contractors continue to work throughout the building...
Download PDF →