North County Campus Center – 7-15-16 Weekly Construction Update
Work this week: The concrete contractor is continuing to install the rebar and set anchor bolt templates for the column pad footings...
Download PDF →June 2016 Monthly Project Update
Monthly status update on all existing Measure L projects.
Download PDF →North County Campus Center – 7-08-16 Weekly Construction Update
Work this week: The concrete contractor has completed the excavation for the column pad concrete footings and elevator pit and has started the installation of rebar and pre-fabrication of anchor bolt templates for the column pad footings...
Download PDF →North County Campus Center – 7-01-16 Weekly Construction Update
Work this week: The underground utilities and 8” fire line are both complete; and the concrete contractor continues excavation for the column pad concrete footings and the concrete grade beams...
Download PDF →North County Campus Center – 6-24-16 Weekly Construction Update
Work this week: The utilities contractor completed the installation, tested and started backfill of the new 8” fire line...
Download PDF →North County Campus Center – 6-17-16 Weekly Construction Update
Work this week: The utilities contractor began trenching and installation of the fire water line...
Download PDF →North County Campus Center – 6-10-16 Weekly Construction Update
Work this week: The grading contractor completed bringing the building pad back up to the required subgrade elevation...
Download PDF →May 2016 Monthly Project Update
Monthly status update on all existing Measure L projects.
Download PDF →North County Campus Center – 6-03-16 Weekly Construction Update
Work this week: The grading contractor continues the installation of compacted fill dirt to bring the building pad up to the required subgrade elevation...
Download PDF →North County Campus Center – 5-27-16 Weekly Construction Update
Work this week: The grading contractor completed the over-excavation, scarified and re-compaction of the subgrade of the building pad, and began installing compacted fill to bring the pad back up to the required subgrade elevation...
Download PDF →