Cuesta College Bond Info

  • About Measure L
    • General Info
    • Ballot Language
    • Frequently Asked Questions
  • Project Info
    • Project Overview
    • Projects: 1st Issuance
    • Projects: 2nd Issuance
    • Projects: 3rd Issuance
    • Projects: 4th Issuance
    • Featured Image Gallery
    • Construction Alerts
    • SLO Campus Map
    • North County Map
  • Oversight Committee
  • Business Opportunities
    • Contractor Prequalification
    • Business RFQs/RFPs
    • Bid Timelines
    • Online Plan Room
  • News
  • Contact

Category: North County Campus Center

August 2016 Monthly Project Update

September 12, 2016 · North County Campus Center, SLO Campus Instructional Building

Monthly status update on all existing Measure L projects.

Download PDF →

North County Campus Center – 9-09-16 Weekly Construction Update

September 9, 2016 · Construction Updates, North County Campus Center

Work this week: The contractors have completed the installation and backfill of under slab utilities and conduit...

Download PDF →

North County Campus Center – 9-02-16 Weekly Construction Update

September 2, 2016 · Construction Updates, North County Campus Center

Work this week: The plumbing contractor completed the sub-slab waste piping installation and backfilled the trenches...

Download PDF →

North County Campus Center – 8-26-16 Weekly Construction Update

August 26, 2016 · Construction Updates, North County Campus Center, Uncategorized

Work this week: The plumbing and electrical contractors are continuing layout, excavation, installation, testing and backfill of under slab pipe and conduit, with the under slab waste pipe nearing completion...

Download PDF →

North County Campus Center – 8-19-16 Weekly Construction Update

August 19, 2016 · Construction Updates, North County Campus Center

Work this week: The plumbing and electrical contractors are continuing layout, excavation, installation, testing and backfill of underslab pipe and conduit...

Download PDF →

North County Campus Center – 8-12-16 Weekly Construction Update

August 12, 2016 · Construction Updates, North County Campus Center

Work this week: The plumbing and electrical contractors continued layout, began utility trenching and conduit installation at the electrical room and main duct bank...

Download PDF →

North County Campus Center – 8-05-16 Weekly Construction Update

August 5, 2016 · Construction Updates, North County Campus Center

Work this week: The plumbing and electrical contractors continued layout and began trenching for the below-slab utility installation...

Download PDF →

July 2016 Monthly Project Update

August 1, 2016 · North County Campus Center, SLO Campus Instructional Building

Monthly status update on all existing Measure L projects.

Download PDF →

North County Campus Center – 7-29-16 Weekly Construction Update

July 29, 2016 · Construction Updates, North County Campus Center

Work this week: The concrete contractor completed setting forms and anchor bolts and placed 142 cubic yards of concrete at the structural steel column pad footings.

Download PDF →

North County Campus Center – 7-22-16 Weekly Construction Update

July 22, 2016 · Construction Updates, North County Campus Center

Work this week: The concrete contractor has completed installation of the rebar and verification of the anchor bolt placement in preparation for the concrete placement of the structural steel column pad footings next week...

Download PDF →
← Newer Posts
Older Posts →
  • Search News:

    Search the Cuesta College Bond Website:
  • News Categories

    • Articles
    • Construction Updates
      • 9100 Roofing-HVAC
      • District Wide Asphalt
      • District Wide Upgrades
      • District Wide Upgrades 2nd
      • District-Wide Wayfinding
      • EV Charging Stations
      • Hollister Adobe Stabilization
      • Interim Housing
      • NCC Campus-wide
      • NCC Early Childhood Education Center
      • NCC Parking Lot 10 and Monument Sign
      • North County Campus Center
      • North County Sitework
      • Planning – Aquatic Center
      • Repairs – HVAC/Roofs 1100, 4500, and 4600
      • SLO 1000 Complex Renovations
      • SLO 2000 Complex Renovations
      • SLO Campus Center
      • SLO Campus Center Design
      • SLO Campus Instructional Building
      • SLO Data Center
      • SLO HVAC/Roofs Phase 1
      • SLO HVAC/Roofs Phase 2
      • SLO Switchgear Replacement
      • Technology Upgrades 2nd
      • Technology Upgrades 3rd
      • Upgrades – Aquatic Center
    • Press Releases
    • Uncategorized

Back To Top

Cuesta College Logo
Search the Cuesta College Bond Website: