North County Campus Center – 11-04-16 Weekly Construction Update
Work this week: The majority of the structural steel members for sequences 1-5 have been set...
Download PDF →October 2016 Monthly Project Update
Monthly status update on all existing Measure L projects.
Download PDF →North County Campus Center – 10-28-16 Weekly Construction Update
Work this week: The erection of the structural steel is continuing with sequences 1-4 approximately 95% complete...
Download PDF →North County Campus Center – 10-21-16 Weekly Construction Update
Work this week: The site utilities contractors continue to install and backfill sewer laterals and electrical duct banks...
Download PDF →North County Campus Center – 10-14-16 Weekly Construction Update
Work this week: Concrete crews placed 42 cubic yards of concrete at the depressed slab area (kitchen and restrooms) of the building...
Download PDF →September 2016 Monthly Project Update
Monthly status update on all existing Measure L projects.
Download PDF →North County Campus Center – 10-07-16 Weekly Construction Update
Work this week: The construction teams placed and finished approx. 275 cubic yards of concrete for the building’s slab on grade...
Download PDF →North County Campus Center – 9-30-16 Weekly Construction Update
Work this week: The concrete contractor completed the installation of bar reinforcing and column blockouts for the building slab on grade scheduled to be placed Monday, 10/03/16...
Download PDF →North County Campus Center – 9-23-16 Weekly Construction Update
Work this week: The contractor completed the smoke testing of the sub slab vapor barrier...
Download PDF →North County Campus Center – 9-16-16 Weekly Construction Update
Work this week: The contractors have completed setting all of the below slab utilities to clear the way for the installation of the below slab vapor barrier...
Download PDF →