Cuesta College Bond Info

  • About Measure L
    • General Info
    • Ballot Language
    • Frequently Asked Questions
  • Project Info
    • Project Overview
    • Projects: 1st Issuance
    • Projects: 2nd Issuance
    • Projects: 3rd Issuance
    • Projects: 4th Issuance
    • Featured Image Gallery
    • Construction Alerts
    • SLO Campus Map
    • North County Map
  • Oversight Committee
  • Business Opportunities
    • Contractor Prequalification
    • Business RFQs/RFPs
    • Bid Timelines
    • Online Plan Room
  • News
  • Contact

Category: North County Campus Center

December 2016 Monthly Project Update

January 1, 2017 · Construction Updates, North County Campus Center, SLO Campus Instructional Building

Monthly status update on all existing Measure L projects.

Download PDF →

North County Campus Center – 12-23-16 Weekly Construction Update

December 23, 2016 · Construction Updates, North County Campus Center

Work this week: The plumbing, HVAC, and electrical contractors continue to install hanger inserts and pipe/conduit-penetration sleeves through the second floor decking...

Download PDF →

North County Campus Center – 12-16-16 Weekly Construction Update

December 16, 2016 · Construction Updates, North County Campus Center

Work this week: The Plumbing, HVAC, and Electrical contractors have started to install hanger inserts and pipe/conduit penetration sleeves through the second floor decking...

Download PDF →

North County Campus Center – 12-09-16 Weekly Construction Update

December 9, 2016 · Construction Updates, North County Campus Center

Work this week: The structural steel erector continues the installation of the mansard framing and has started the architectural louvers at the front entry...

Download PDF →

North County Campus Center – 12-02-16 Weekly Construction Update

December 2, 2016 · Construction Updates, North County Campus Center

Work this week: The structural steel erector continues to weld structural steel beam connections...

Download PDF →

November 2016 Monthly Project Update

December 1, 2016 · Construction Updates, North County Campus Center, SLO Campus Instructional Building

Monthly status update on all existing Measure L projects.

Download PDF →

Cuesta College holds ‘topping out’ ceremony at new North County Campus Center (video)

November 30, 2016 · North County Campus Center, Uncategorized

One of the last beams is moved into place on the steel frame of a new structure at Cuesta College's North Campus campus on Nov. 8, 2016. The new center will house a variety of student services as well as...

Read More →

North County Campus Center – 11-25-16 Weekly Construction Update

November 25, 2016 · Construction Updates, North County Campus Center

Work this week: The structural steel erector continues to weld structural steel beam connections this week...

Download PDF →

North County Campus Center – 11-18-16 Weekly Construction Update

November 18, 2016 · Construction Updates, North County Campus Center

Work this week: The structural steel erector continues to install and weld the structural steel and mansard framing members...

Download PDF →

North County Campus Center – 11-11-16 Weekly Construction Update

November 11, 2016 · Construction Updates, North County Campus Center

Work this week: A successful topping out ceremony was held on 11/08/16...

Download PDF →
← Newer Posts
Older Posts →
  • Search News:

    Search the Cuesta College Bond Website:
  • News Categories

    • Articles
    • Construction Updates
      • 9100 Roofing-HVAC
      • District Wide Asphalt
      • District Wide Upgrades
      • District Wide Upgrades 2nd
      • District-Wide Wayfinding
      • EV Charging Stations
      • Hollister Adobe Stabilization
      • Interim Housing
      • NCC Campus-wide
      • NCC Early Childhood Education Center
      • NCC Parking Lot 10 and Monument Sign
      • North County Campus Center
      • North County Sitework
      • Planning – Aquatic Center
      • Repairs – HVAC/Roofs 1100, 4500, and 4600
      • SLO 1000 Complex Renovations
      • SLO 2000 Complex Renovations
      • SLO Campus Center
      • SLO Campus Center Design
      • SLO Campus Instructional Building
      • SLO Data Center
      • SLO HVAC/Roofs Phase 1
      • SLO HVAC/Roofs Phase 2
      • SLO Switchgear Replacement
      • Technology Upgrades 2nd
      • Technology Upgrades 3rd
      • Upgrades – Aquatic Center
    • Press Releases
    • Uncategorized

Back To Top

Cuesta College Logo
Search the Cuesta College Bond Website: