North County Campus Center – 03-10-17 Weekly Construction Update
Work this week: The concrete contractor completed curbs for the perimeter exterior walls and excavated, installed reinforcing and placed concrete at the CMU footings...
Download PDF →North County Campus Center – 03-03-17 Weekly Construction Update
Work this week: The concrete contractor continued forming and placing concrete curbs at the perimeter of the exterior walls...
Download PDF →February 2017 Monthly Project Updates
Monthly status update on all existing Measure L projects.
Download PDF →North County Campus Center – 02-24-17 Weekly Construction Update
Work this week: The concrete contractor continues the exterior concrete curb formwork, rebar installation, and placed concrete at half of the curbs this week...
Download PDF →North County Campus Center – 02-03-17 Weekly Construction Update
Work this week: The concrete contractor has removed the second deck formwork and has begun to form the exterior wall curbing...
Download PDF →January 2017 Monthly Project Updates
Monthly status update on all existing Measure L projects.
Download PDF →North County Campus Center – 01-27-17 Weekly Construction Update
Work this week: The second floor slab on deck concrete was poured along with the last of the slab closure concrete pours which completes all of the building structural concrete...
Download PDF →North County Campus Center – 01-20-17 Weekly Construction Update
Work this week: The concrete contractor continued installation of reinforcing the second floor deck, completed formwork on the second floor depressed slab areas, and placed the slab-on-grade closure pour #3...
Download PDF →North County Campus Center – 01-13-17 Weekly Construction Update
Work this week: The concrete contractor continued installation of reinforcing at the second floor deck slab; continued formwork on the second floor and 1st floor block outs; and placed an additional slab on grade closure section...
Download PDF →North County Campus Center – 01-06-17 Weekly Construction Update
Work this week: The slab-on-grade reinforcing, edge forms, and vapor barrier are complete, and reinforcing is being installed on the second floor deck...
Download PDF →