North County Campus Center – 04-07-17 Weekly Construction Update
Work this week: The framing/plaster contractor continues interior and exterior framing on the first and second floors, and continues scaffold installation around the perimeter of the building...
Download PDF →March 2017 Monthly Project Update
Monthly status update on all existing Measure L projects.
Download PDF →North County Campus Center – 03-31-17 Weekly Construction Update
Work this week: The CMU (concrete masonry units) blocks were installed at the front entry...
Download PDF →North County Campus Center – 03-24-17 Weekly Construction Update
Work this week: Installation of the concrete masonry walls at the equipment yard and fine arts patio started this week...
Download PDF →North County Campus Center – 03-17-17 Weekly Construction Update
Work this week: The concrete contractor completed the concrete masonry unit (CMU) wall reinforcing and placed concrete...
Download PDF →North County Campus Center – 03-10-17 Weekly Construction Update
Work this week: The concrete contractor completed curbs for the perimeter exterior walls and excavated, installed reinforcing and placed concrete at the CMU footings...
Download PDF →North County Campus Center – 03-03-17 Weekly Construction Update
Work this week: The concrete contractor continued forming and placing concrete curbs at the perimeter of the exterior walls...
Download PDF →February 2017 Monthly Project Updates
Monthly status update on all existing Measure L projects.
Download PDF →North County Campus Center – 02-24-17 Weekly Construction Update
Work this week: The concrete contractor continues the exterior concrete curb formwork, rebar installation, and placed concrete at half of the curbs this week...
Download PDF →North County Campus Center – 02-03-17 Weekly Construction Update
Work this week: The concrete contractor has removed the second deck formwork and has begun to form the exterior wall curbing...
Download PDF →