North County Campus Center – 10-20-17 Weekly Construction Update
Work this week: The project’s contractors continue to install piping and controls’ wiring for the HVAC equipment on the rooftop...
Download PDF →North County Campus Center – 10-13-17 Weekly Construction Update
Work this week: Data and power cables are being pulled throughout various locations in the building. Installation of the curtain wall at the southern elevation has continued, and tile preparation and installation is scheduled to begin...
Download PDF →North County Campus Center – 10-06-17 Weekly Construction Update
Work this week: Contractors continue the installation of the drywall, insulation, acoustical ceilings, HVAC, electrical, painting, communications, data and fire protection on the 1st and 2nd floors...
Download PDF →September 2017 Monthly Project Update
Monthly status update on all existing Measure L projects.
Download PDF →North County Campus Center – 09-28-17 Weekly Construction Update
Work this week: Contractors continue the installation of the drywall, insulation, HVAC, electrical, painting, communications, Data and Fire Protection on the 1st and 2nd floors...
Download PDF →North County Campus Center – 09-22-17 Weekly Construction Update
Work this week: Drywall installation, tape, texture, and finish continues on the 1st and 2nd floor with interior paint following along...
Download PDF →North County Campus Center – 09-15-17 Weekly Construction Update
Work this week: Drywall installation has started at the computer lab skylight opening and continues throughout the building...
Download PDF →North County Campus Center – 09-08-17 Weekly Construction Update
Work this week: Plaster, drywall, interior and exterior paint, and acoustical ceiling installation continue to progress...
Download PDF →North County Campus Center – 09-01-17 Weekly Construction Update
Work this week: Drywall, paint, and acoustical ceiling installation continue to progress and the K-13 spray acoustical insulation was complete in the in the main entry and the cafeteria...
Download PDF →August 2017 Monthly Project Update
Monthly status update on all existing Measure L projects.
Download PDF →