Interim Housing – 8-3-15 Weekly Construction Update
August 3, 2015 · Construction Updates, Interim Housing
Work this week: Completion of punch list items. Owner move-in continues to progress...
Download PDF →Interim Housing – 7-28-15 Weekly Construction Update
July 28, 2015 · Construction Updates, Interim Housing
Work this week: Completing interior finishes and dropping ceiling tiles...
Download PDF →Interim Housing – 7-13-15 Weekly Construction Update
July 13, 2015 · Construction Updates, Interim Housing
Work this week: Electrical and low-voltage work continues, with fire alarm devices installed...
Download PDF →Interim Housing – 7-9-15 Weekly Construction Update
July 9, 2015 · Construction Updates, Interim Housing
Work this week: All portables have been delivered. Electrical and low-voltage work continues to progress...
Download PDF →Interim Housing – 6-29-15 Weekly Construction Update
June 29, 2015 · Construction Updates, Interim Housing
Work this week: Finish setting and installing portables with ongoing electrical and low-voltage work...
Download PDF →Interim Housing – 6-25-15 Weekly Construction Update
June 25, 2015 · Construction Updates, Interim Housing
Work this week: Finish setting and installing portables with ongoing electrical and low-voltage work...
Download PDF →Interim Housing – 6-19-15 Weekly Construction Update
June 19, 2015 · Construction Updates, Interim Housing
Started delivery of the portables June 8th and will continue through the end of June 2015...
Download PDF →Interim Housing – 6-8-15 Weekly Construction Update
June 8, 2015 · Construction Updates, Interim Housing
Updates and activities that may impact campus operation - Week of June 8, 2015
Download PDF →