4k, 5k, 6k Restroom & Drinking Fountain ADA Upgrades – 10-26-22 Weekly Construction Update
Work this week: Contractor installed tile in Building 4200. Ceilings in Building 4600 are currently being painted. Sheet rock has been installed in Building 4100, and the tile crew is scheduled to start tiling this week. Framing work in Bldg....
Download PDF →September Monthly Project Updates
Monthly status update.
Download PDF →4k, 5k, 6k Restroom & Drinking Fountain ADA Upgrades – 09-09-22 Weekly Construction Update
Work this week: Contractor is currently performing demolition in building 5100. All interior finishes have been removed from the men’s restroom, and MEC is working to remove the remaining floor tile on the women’s side. MEC is also performing concrete...
Download PDF →July Monthly Project Updates
Monthly status update.
Download PDF →Building 7500 ADA Site Improvements — 07-15-22 Weekly Construction Update
Work this week: The contractor broke ground this week and completed demolition in the parking are. Construction team began grading, compacting base, and digging footings for the ramp.
Download PDF →June Monthly Project Updates
Monthly status update.
Download PDF →Restroom/Drinking Fountain ADA Upgrades – 05-06-22 Weekly Construction Update
Work this week: Contractor completed tile installation in Building 4000 restrooms. Construction team poured concrete at Building 7100 and 4000. Plumbing contractor began installation of drinking fountains at the Tennis Court area.
Download PDF →April Monthly Project Update – SLO Campus Police Department Renovation
Monthly status update on SLO Campus Police Department Renovation project.
Download PDF →April Monthly Project Update – SLO Campus RR & Drinking Fountain ADA Upgrades
Monthly status update on SLO Campus Restrooms/Drinking Fountain ADA Upgrades projects.
Download PDF →Restroom/Drinking Fountain ADA Upgrades – 04-15-22 Weekly Construction Update
Work this week: Contractor completed the demolition in Building 7100. Construction team installed drywall in Building 4000. Building 4000 has been prepped to receive tile.