December Monthly Project Updates
Monthly status update.
Download PDF →4k, 5k, 6k Restroom & Drinking Fountain ADA Upgrades – 12-23-22 Weekly Construction Update
Work this week: Contractor has substantially completed 6100 restrooms and is preparing for punch walk next week. Tile is in progress at 5100, and drywall/sheetrock has been hung in 4300.
Download PDF →4k, 5k, 6k Restroom & Drinking Fountain ADA Upgrades – 12-16-22 Weekly Construction Update
Work this week: Contractor has completed tile in 6100 restrooms and plumbing fixtures/partitions are being installed. Framing in 4300 is substantially complete and above ground plumbing/electrical is in progress. The tile crew also started floating floors in 5100 today.
Download PDF →4k, 5k, 6k Restroom & Drinking Fountain ADA Upgrades – 12-9-22 Weekly Construction Update
Work this week: Restrooms at 4100 have been completed and punched. Fire alarm test and punch list items are still pending. Contractor is currently framing in 4300 and tile is being installed in 6100.
Download PDF →4k, 5k, 6k Restroom & Drinking Fountain ADA Upgrades – 12-2-22 Weekly Construction Update
Work this week: Contractor installed fire alarm in building 4100 and began clearing conduit pathways to 4200. Underground plumbing and concrete patch has been completed in building 4300 and tile crew has installed tile at exterior drinking fountains.
Download PDF →November Monthly Project Updates
Monthly status update.
Download PDF →4k, 5k, 6k Restroom & Drinking Fountain ADA Upgrades – 11-25-22 Weekly Construction Update
Work this week: Contractor continued installation of lath and began floating floors in building 6100. Underground plumbing is ongoing in building 4300.
Download PDF →4k, 5k, 6k Restroom & Drinking Fountain ADA Upgrades – 11-18-22 Weekly Construction Update
Work this week: Contractor hung drywall lids and installed lath system at Building 6100. Plumbing fixtures have been installed in 4100 and toilet partitions are in progress. Demolition work at Building 4300 has been completed and underground plumbing work remains...
Download PDF →4k, 5k, 6k Restroom & Drinking Fountain ADA Upgrades – 11-11-22 Weekly Construction Update
Work this week: Contractor installed restroom accessories in Building 4200 and 4600. Tile work in Building 4100 restrooms was completed. Framing work in Building 6100, remains ongoing.
Download PDF →4k, 5k, 6k Restroom & Drinking Fountain ADA Upgrades – 11-4-22 Weekly Construction Update
Work this week: Contractor installed plumbing fixtures and lighting in building 4200 and 4600. Walls have been taped, floors have been floated and sealed in 4100 in preparation for tiling. Framing work in 6100 is ongoing.
Download PDF →