Cuesta College Bond Info

  • About Measure L
    • General Info
    • Ballot Language
    • Frequently Asked Questions
  • Project Info
    • Project Overview
    • Projects: 1st Issuance
    • Projects: 2nd Issuance
    • Projects: 3rd Issuance
    • Projects: 4th Issuance
    • Featured Image Gallery
    • Construction Alerts
    • SLO Campus Map
    • North County Map
  • Oversight Committee
  • Business Opportunities
    • Contractor Prequalification
    • Business RFQs/RFPs
    • Bid Timelines
    • Online Plan Room
  • News
  • Contact

Category: District Wide Upgrades 2nd

December Monthly Project Updates

December 31, 2022 · District Wide Upgrades 2nd, SLO Switchgear Replacement, Technology Upgrades 3rd

Monthly status update.

Download PDF →

4k, 5k, 6k Restroom & Drinking Fountain ADA Upgrades – 12-23-22 Weekly Construction Update

December 23, 2022 · District Wide Upgrades 2nd

Work this week: Contractor has substantially completed 6100 restrooms and is preparing for punch walk next week. Tile is in progress at 5100, and drywall/sheetrock has been hung in 4300.

Download PDF →

4k, 5k, 6k Restroom & Drinking Fountain ADA Upgrades – 12-16-22 Weekly Construction Update

December 16, 2022 · District Wide Upgrades 2nd

Work this week: Contractor has completed tile in 6100 restrooms and plumbing fixtures/partitions are being installed. Framing in 4300 is substantially complete and above ground plumbing/electrical is in progress. The tile crew also started floating floors in 5100 today.

Download PDF →

4k, 5k, 6k Restroom & Drinking Fountain ADA Upgrades – 12-9-22 Weekly Construction Update

December 9, 2022 · District Wide Upgrades 2nd

Work this week: Restrooms at 4100 have been completed and punched. Fire alarm test and punch list items are still pending. Contractor is currently framing in 4300 and tile is being installed in 6100.

Download PDF →

4k, 5k, 6k Restroom & Drinking Fountain ADA Upgrades – 12-2-22 Weekly Construction Update

December 2, 2022 · District Wide Upgrades 2nd

Work this week: Contractor installed fire alarm in building 4100 and began clearing conduit pathways to 4200. Underground plumbing and concrete patch has been completed in building 4300 and tile crew has installed tile at exterior drinking fountains.

Download PDF →

November Monthly Project Updates

November 30, 2022 · District Wide Upgrades 2nd, SLO Switchgear Replacement

Monthly status update.

Download PDF →

4k, 5k, 6k Restroom & Drinking Fountain ADA Upgrades – 11-25-22 Weekly Construction Update

November 25, 2022 · District Wide Upgrades 2nd

Work this week: Contractor continued installation of lath and began floating floors in building 6100. Underground plumbing is ongoing in building 4300.

Download PDF →

4k, 5k, 6k Restroom & Drinking Fountain ADA Upgrades – 11-18-22 Weekly Construction Update

November 18, 2022 · District Wide Upgrades 2nd

Work this week: Contractor hung drywall lids and installed lath system at Building 6100. Plumbing fixtures have been installed in 4100 and toilet partitions are in progress. Demolition work at Building 4300 has been completed and underground plumbing work remains...

Download PDF →

4k, 5k, 6k Restroom & Drinking Fountain ADA Upgrades – 11-11-22 Weekly Construction Update

November 11, 2022 · District Wide Upgrades 2nd

Work this week: Contractor installed restroom accessories in Building 4200 and 4600. Tile work in Building 4100 restrooms was completed. Framing work in Building 6100, remains ongoing.

Download PDF →

4k, 5k, 6k Restroom & Drinking Fountain ADA Upgrades – 11-4-22 Weekly Construction Update

November 4, 2022 · District Wide Upgrades 2nd

Work this week: Contractor installed plumbing fixtures and lighting in building 4200 and 4600. Walls have been taped, floors have been floated and sealed in 4100 in preparation for tiling. Framing work in 6100 is ongoing.

Download PDF →
← Newer Posts
Older Posts →
  • Search News:

    Search the Cuesta College Bond Website:
  • News Categories

    • Articles
    • Construction Updates
      • 9100 Roofing-HVAC
      • District Wide Asphalt
      • District Wide Upgrades
      • District Wide Upgrades 2nd
      • District-Wide Wayfinding
      • EV Charging Stations
      • Hollister Adobe Stabilization
      • Interim Housing
      • NCC Campus-wide
      • NCC Early Childhood Education Center
      • NCC Parking Lot 10 and Monument Sign
      • North County Campus Center
      • North County Sitework
      • Planning – Aquatic Center
      • Repairs – HVAC/Roofs 1100, 4500, and 4600
      • SLO 1000 Complex Renovations
      • SLO 2000 Complex Renovations
      • SLO Campus Center
      • SLO Campus Center Design
      • SLO Campus Instructional Building
      • SLO Data Center
      • SLO HVAC/Roofs Phase 1
      • SLO HVAC/Roofs Phase 2
      • SLO Switchgear Replacement
      • Technology Upgrades 2nd
      • Technology Upgrades 3rd
      • Upgrades – Aquatic Center
    • Press Releases
    • Uncategorized

Back To Top

Cuesta College Logo
Search the Cuesta College Bond Website: