Early Childhood Education – 07-05-19 Weekly Construction Update
Work This Week: The connection to the gas line was completed and the chilled water lines to the building were finished…
Work This Week: The connection to the gas line was completed and the chilled water lines to the building were finished…
Monthly status update on all existing Measure L projects.
Work This Week: The reinforcing concrete slab will be installed for the scheduled pour on Tuesday…
Work This Week: Installation of the vapor and gas barriers has been completed…
Work This Week: Final grading of the parking lot in progress…
Work This Week: This week the forms were stripped from the footing concrete pour…
Monthly status update on all existing Measure L projects.
Work This Week: Work on the reinforcing the footings, hold-downs, and formwork continued…
Work This Week: Work on the footing reinforcing, hold- downs, and formwork continued…
Work This Week: The underground electrical and storm drain plumbing have been completed in the parking lot…