2000 Complex Renovations Project – 01-10-20 Weekly Construction Update
Work this week: General contractor completed the Switchgear project…
Work this week: General contractor completed the Switchgear project…
Monthly status update on all existing Measure L projects.
Work This Week: The HVAC contractor has finished installing the new ductwork for HVAC units on the roof of Building 1200…
Monthly status update on all existing Measure L projects.
Work This Week: The roofing contractor has completed installation of the new single ply roofing system…
Work This Week: The HVAC contractor has installed new platforms for the HVAC equipment and has installed four new roof drains…
Monthly status update on all existing Measure L projects.
Work This Week: The roofing contractor has finished cleaning up of roofing materials and has loaded the roof with insulation and Densdeck for the new roof install…
Work this week: The roofing contractor has completed the demolition of the existing roof, and all conduit installation is completed…
Monthly status update on all existing Measure L projects.