North County Campus Parking Lot 10 and Site Improvements – 10-08-21 Weekly Construction Update
Work this week: The contractor is detailing the new concrete and working on the punch list.
Work this week: The contractor is detailing the new concrete and working on the punch list.
Work this week: The decomposed granite in the courtyard area was compacted and irrigation controller was set in place. Benches were set & pre-punch cleanup work has begun.
Work this week: Contractor placed sod on the East end of the new quad. Planting and bark placement work remains ongoing.
Work this week: Planting of trees & shrubs, as well as placement of the drip irrigation and rock in the dry creek remains ongoing.
Work this week: The remaining concrete for the main walkway was poured. The landscape contractor began planting trees.
Work this week: Contractor spread planting material throughout the site. The rock in the dry creek area was filled in.
Monthly status update on all existing Measure L projects.
Work this week: The contractor striped the parking lot and added the bark in the planters. The final punch items are now being addressed.
Work this week: Concrete was poured to set the steel frames for dry creek crossings in place. The concrete curb bordering the dry creek was also poured in place. Irrigation installation work is ongoing. The landscape contractor began prepping the soils for planting materials. Additional reinforcing steel was also placed for the main 25’ walkway […]
Work this week: Contractor poured additional concrete for the main walkway in the quad area. Irrigation installation & fine grading work remains ongoing.