Pool Equipment Room – 10-30-20 Weekly Construction Update
Work this week: The general contractor installed the new steel support posts and removed the temporary shoring in the pool equipment room.
Work this week: The general contractor installed the new steel support posts and removed the temporary shoring in the pool equipment room.
Work this week: The general contractor installed shoring and removed the existing wooden posts.
Monthly status update on all existing Measure L projects.
Monthly status update on all existing Measure L projects.
Monthly status update on all existing Measure L projects.
Work this week: Construction crews have completed all work in the pool equipment room…
Work this week: Construction crews are continuing to work on the electrical in the pool equipment room; testing, and commissioning…
Work this week: Construction crews are continuing to work on the electrical in the pool equipment room…
Work this week: Construction crews are continuing to work on the electrical in the pool equipment room…
Work this week: The perimeter grating for the teaching pool gutter has been completed…