Early Childhood Education – 10-25-19 Weekly Construction Update
Work this week: General contractor continued work on cold-formed metal framing phase of the main building…
Work this week: General contractor continued work on cold-formed metal framing phase of the main building…
Monthly status update on all existing Measure L projects.
Monthly status update on all existing Measure L projects.
Work This Week: The wall framing installation will be ongoing this week…
Work This Week: Parking lot striping is complete and handicap signage is installed. Planting is progressing in the parking lot…
Work This Week: The contractor worked on structural steel and the installation of the metal wall tracks…
Work This Week: Work on structural steel continued, along with installation of the metal wall tracks…
Monthly status update on all existing Measure L projects.
Work This Week: The curbs and gutters were finished in the parking lot and base material is being placed…
Work This Week: The building slab has been poured…