NCC IT Backup Generator – 03-12-21 Weekly Update
Work this week: Contractor completed conduit runs. Concrete was replaced at the walkway and poured at the generator pad in the chiller yard.
Work this week: Contractor completed conduit runs. Concrete was replaced at the walkway and poured at the generator pad in the chiller yard.
Work this week: Circuiting was coordinated for the new light poles. Power and Data stations were placed at the locations of the future bus shelters.
Work this week: Stripping work for the right turn lane leading to the drive aisle entrance was completed. The electrician installed uplights in the planter areas.
Monthly status update on all existing Measure L projects.
Work this week: The contractor placed their second lift of asphalt in the traffic areas.
Work this week: Landscaping contractor began trenching and installing irrigation lines.
Work this week: New pedestrian flat work was poured at the walkway connecting Parking Lot 10 to the Campus Center. The second lift of asphalt paving is scheduled for next week.
Monthly status update on all existing Measure L projects.
Work this week: New concrete was poured at the front of the Campus Center. Additional concrete was poured at the front drive aisle entrance off Buena Vista Drive.
Work this week: New concrete was poured at the front of the Campus Center. New curb, gutter, and accessible pathways were also poured at the entrance to Parking Lot 11.