Restroom/Drinking Fountain ADA Upgrades – 04-01-22 Weekly Construction Update
Work this week: Contractor mobilized and began demolition in Buildings 4000, 1400 and 7100. MEP rough in work began in Building 4000 and 1400.
Work this week: Contractor mobilized and began demolition in Buildings 4000, 1400 and 7100. MEP rough in work began in Building 4000 and 1400.
Work this week: The contractor installed the emergency stop button on the MTS and the gas regulator.
Work this week: The wiring work for the manual and automatic transfer switches has been completed. Generator was received and set it in place.
Work this week: The contractor set the automatic transfer switch, and the manual transfer switch, and began pulling wiring through the previously installed conduits.
Monthly status update on all existing Measure L projects.
Work this week: Conduit boxes were placed and conduit was ran above ceiling from the electrical room to the server room. The contractor began work on the gas feed for the generator.
Work this week: Contractor completed conduit runs. Concrete was replaced at the walkway and poured at the generator pad in the chiller yard.
Work this week: General contractor installed all new electrical primary gear…
Work This Week: The contractor completed the campus wide shut down allowing them to do the coring needed to get their conduits into the vaults…
Work This Week: The 12KV primary contractor has been locating conduit ducts and other infrastructure…