NCC Parking Lot 10 & Site Improvements – 03-05-21 Weekly Construction Update
March 5, 2021 · District Wide Asphalt, NCC Parking Lot 10 and Monument Sign, North County Sitework
Work this week: Stripping work for the right turn lane leading to the drive aisle entrance was completed. The electrician installed uplights in the planter areas.