Data Center Project – 01-04-19 Weekly Construction Update
Work this week: Construction crews resumed the installation and backfilling of the new sewer line and are exporting the spoils...
Download PDF →December 2018 Monthly Project Update
Monthly status update on all existing Measure L projects.
Download PDF →Data Center Project – 12-28-18 Weekly Construction Update
Work this week: Construction crews the under slab work and are prepping for grade beam install, and includes the installation of rebar, then the pouring of the concrete...
Download PDF →Data Center Project – 12-14-18 Weekly Construction Update
Work this week: Construction crews started laying out and trenching for the under slab (foundation) sewer piping...
Download PDF →Data Center Project – 12-07-18 Weekly Construction Update
Work this week: Weather slowed progress of the site work, however, construction crews were able to open and inspect current condition and determine tie-in areas for the new utilities and are able to move forward...
Download PDF →November 2018 Monthly Project Update
Monthly status update on all existing Measure L projects.
Download PDF →Data Center Project – 11-26-18 Weekly Construction Update
Work this week: The construction team resumed the install and backfill of utility conduits and trenching, and also the survey and layout of the building...
Download PDF →SLO Data Center– 11-16-18 Weekly Construction Update
Construction crews began drilling and the installation of Data Center’s concrete piers (caissons)..
Download PDF →SLO Data Center– 11-09-18 Weekly Construction Update
Construction crews have completed the competition pool reinforcement and have installed water stops around the drainage piping. Installation of the form for the steps in the teaching pool was completed. Competition-pool surge tank and teaching-pool surge tank reinforcement began. The...
Download PDF →SLO Data Center– 11-02-18 Weekly Construction Update
Construction crews completed the building pad certification, excavation of new utility tie-in, firewater trenching, and the majority of firewater pipe install. Excavation to locate the storm drain for new drain inlet was performed. Also completed was the excavation of a...
Download PDF →