Data Center Project – 03-08-19 Weekly Construction Update
Work this week: The construction team completed pouring the slab on grade concrete, and completed the install of the new gas powered generator in the chiller yard...
Download PDF →February 2019 Monthly Project Update
Monthly status update on all existing Measure L projects.
Download PDF →Data Center Project – 03-01-19 Weekly Construction Update
Work this week: AMG installed the vapor barrier over the grade beams and grids and the completed the underslab-plumbing and electrical work...
Download PDF →Data Center Project – 02-22-19 Weekly Construction Update
Work this week: Early in the week, the construction team continued installing conduit for the building...
Download PDF →Data Center Project – 02-15-19 Weekly Construction Update
Work this week: Due to wet ground conditions, the construction team has postponed recertification of the pad...
Download PDF →Data Center Project – 02-08-19 Weekly Construction Update
Work this week: The construction team installed forms for perimeter curbs and began to pour concrete...
Download PDF →Data Center Project – 02-01-19 Weekly Construction Update
Work this week: Early this week crews installed all the grade beam rebar in preparation for inspection on Wednesday...
Download PDF →Data Center Project – 01-25-19 Weekly Construction Update
Work this week: The general contractor began clearing the grade beam trenches and installing grade rebar...
Download PDF →Data Center Project – 01-14-19 Weekly Construction Update
Work this week: Rain and subsequent wet conditions continued...
Download PDF →Data Center Project – 01-11-19 Weekly Construction Update
Work this week: Weather has slowed progress this week. The electrical contractor preformed preliminary work in the “chiller yard” preparing communication and electrical tie-ins and installing conduits for the new backup generator (lower left pic)...
Download PDF →