Cuesta College Bond Info

  • About Measure L
    • General Info
    • Ballot Language
    • Frequently Asked Questions
  • Project Info
    • Project Overview
    • Projects: 1st Issuance
    • Projects: 2nd Issuance
    • Projects: 3rd Issuance
    • Projects: 4th Issuance
    • Featured Image Gallery
    • Construction Alerts
    • SLO Campus Map
    • North County Map
  • Oversight Committee
  • Business Opportunities
    • Contractor Prequalification
    • Business RFQs/RFPs
    • Bid Timelines
    • Online Plan Room
  • News
  • Contact

Category: SLO Data Center

Data Center Project – 05-24-19 Weekly Construction Update

May 24, 2019 · Construction Updates, SLO Data Center

Work this week: The structural exterior and interior walls are now 90% complete...

Download PDF →

Data Center Project – 05-17-19 Weekly Construction Update

May 17, 2019 · Construction Updates, SLO Data Center

Work this week: The general contractor is detailing their cold formed metal framing this week...

Download PDF →

Data Center Project – 05-03-19 Weekly Construction Update

May 3, 2019 · Construction Updates, SLO Data Center

Work this week: Metal Framing is in process. The contractor has achieved 75% completion on the roof joists and are framing the Data Center’s interior walls...

Download PDF →

April 2019 Monthly Project Update

May 1, 2019 · Construction Updates, NCC Early Childhood Education Center, SLO 1000 Complex Renovations, SLO Data Center, Upgrades - Aquatic Center

Monthly status update on all existing Measure L projects.

Download PDF →

Data Center Project – 04-26-19 Weekly Construction Update

April 26, 2019 · Construction Updates, SLO Data Center

Work this week: This past week was 100% dedicated to the approval of the roof openings submittal and subsequent to that, roof joist installation (pics 1,2 & 3). Joists are the roof cross “beams” that are the support for everything...

Download PDF →

Data Center Project – 04-05-19 Weekly Construction Update

April 5, 2019 · Construction Updates, SLO Data Center

Work this week: The construction team began installing the new gas line across the north edge of the project...

Download PDF →

March 2019 Monthly Project Update

April 1, 2019 · Construction Updates, NCC Early Childhood Education Center, SLO 1000 Complex Renovations, SLO Data Center, Technology Upgrades 2nd, Upgrades - Aquatic Center

Monthly status update on all existing Measure L projects.

Download PDF →

Data Center Project – 03-29-19 Weekly Construction Update

March 29, 2019 · Construction Updates, SLO Data Center

Work this week: Construction crews continue cold formed metal framing...

Download PDF →

Data Center Project – 03-22-19 Weekly Construction Update

March 22, 2019 · Construction Updates, SLO Data Center

Work this week: This week, the construction team began the cold formed metal framing for Data Center...

Download PDF →

Data Center Project – 03-15-19 Weekly Construction Update

March 15, 2019 · Construction Updates, SLO Data Center

Work this week: This week, the construction team began to frame the Data Center building...

Download PDF →
← Newer Posts
Older Posts →
  • Search News:

    Search the Cuesta College Bond Website:
  • News Categories

    • Articles
    • Construction Updates
      • 9100 Roofing-HVAC
      • District Wide Asphalt
      • District Wide Upgrades
      • District Wide Upgrades 2nd
      • District-Wide Wayfinding
      • EV Charging Stations
      • Hollister Adobe Stabilization
      • Interim Housing
      • NCC Campus-wide
      • NCC Early Childhood Education Center
      • NCC Parking Lot 10 and Monument Sign
      • North County Campus Center
      • North County Sitework
      • Planning – Aquatic Center
      • Repairs – HVAC/Roofs 1100, 4500, and 4600
      • SLO 1000 Complex Renovations
      • SLO 2000 Complex Renovations
      • SLO Campus Center
      • SLO Campus Center Design
      • SLO Campus Instructional Building
      • SLO Data Center
      • SLO HVAC/Roofs Phase 1
      • SLO HVAC/Roofs Phase 2
      • SLO Switchgear Replacement
      • Technology Upgrades 2nd
      • Technology Upgrades 3rd
      • Upgrades – Aquatic Center
    • Press Releases
    • Uncategorized

Back To Top

Cuesta College Logo
Search the Cuesta College Bond Website: