January 2018 Monthly Project Update
Monthly status update on all existing Measure L projects.
Download PDF →SLO Instructional Building – 01-12-18 Weekly Construction Update
Work this week: The project is substantially complete. The furniture and equipment has been installed in the offices and classrooms and are ready for classes to begin at the start of the spring semester..
Download PDF →SLO Instructional Building – 01-05-18 Weekly Construction Update
Work this week: All temporary flooring and finishes protections have been removed...
Download PDF →December 2017 Monthly Project Update
Monthly status update on all existing Measure L projects.
Download PDF →SLO Instructional Building – 12-29-17 Weekly Construction Update
Work this week: The site concrete has been completed and landscaping around the building is near completion. Skate-stoppers have been installed on the concrete seat walls in the plaza area...
Download PDF →SLO Instructional Building – 12-22-17 Weekly Construction Update
Work this week: The keyboard shelves in the second floor lobby were stained, the metal ceiling and lights fixtures were completed, and signage was installed throughout the building...
Download PDF →SLO Instructional Building – 12-15-17 Weekly Construction Update
Work this week: The keyboard shelves in the second floor lobby have been installed...
Download PDF →SLO Instructional Building – 12-08-17 Weekly Construction Update
Work this week: The wood benches on the second floor were stained, roller shades were installed in the exterior offices on the second floor, and the limestone treads have been placed in the exterior stair pans...
Download PDF →November 2017 Monthly Project Update
Monthly status update on all existing Measure L projects.
Download PDF →SLO Instructional Building – 12-01-17 Weekly Construction Update
Work this week: The concrete has continued to be formed and poured in the plaza area...
Download PDF →