The contractor continued forming building perimeter walls on the west 1/3 of the building & started installing under slab vapor barrier. Electrical & Plumbing contractors continued installation of under slab electrical conduit. Site utility contractor was not onsite this week.
Download PDF →SLO Campus Center – 09-15-23 Weekly Construction Update
This week, the contractor started forming building perimeter walls on the west 1/3 of the building. Electrical contractor continued installation of under slab electrical conduit. Elevator Pit drain line & backfill was completed. Site utility contractor continued installation of site...
Download PDF →Monthly Project Status Report August 2023 – Issue 92
SLO Campus Center – 09-08-23 Weekly Construction Update
The contractor poured half of the building pad footings and tie-beam footings. Excavation has started on the 2nd half of the building pad footings and tie-beam footings. Elevator pit wall waterproofing was installed. Site utility contractor continued installation of site...