Early Childhood Education – 12-13-19 Weekly Construction Update
Work this week: General contractor is working on interior walls, and the exterior sheathing...
Download PDF →Early Childhood Education – 12-06-19 Weekly Construction Update
Work this week: General contractor has completed exterior walls...
Download PDF →Early Childhood Education – 11-22-19 Weekly Construction Update
Work this week: General contractor will have final exterior walls of the building completed by end of next week...
Download PDF →November 2019 Monthly Project Update
Monthly status update on all existing Measure L projects.
Download PDF →Early Childhood Education – 11-15-19 Weekly Construction Update
Work this week: The general contractor continued work on the exterior walls of the metal stud framing on main building...
Download PDF →Early Childhood Education – 11-08-19 Weekly Construction Update
Work this week: The general contractor continued work on cold-form metal framing of main building...
Download PDF →October 2019 Monthly Project Update
Monthly status update on all existing Measure L projects.
Download PDF →Early Childhood Education – 11-01-19 Weekly Construction Update
Work this week: General contractor continued work on cold-formed metal framing of main building...
Download PDF →Early Childhood Education – 10-25-19 Weekly Construction Update
Work this week: General contractor continued work on cold-formed metal framing phase of the main building...
Download PDF →September 2019 Monthly Project Update
Monthly status update on all existing Measure L projects.
Download PDF →