Early Childhood Education – 07-04-20 Weekly Construction Update
Work this week: General contractor completed the Sarnafil membrane roof at the mechanical well. Construction team placed the concrete at the site lite stds., and the lobby ceiling received its dark coat of paint.
Download PDF →June 2020 Monthly Project Update
Monthly status update on all existing Measure L projects.
Download PDF →Early Childhood Education – 06-26-20 Weekly Construction Update
Work this week: Roof surfacing at Mechanical well is underway. Construction team will be placing the rebar cages that will be the support for our site light standards.
Download PDF →Early Childhood Education – 06-19-20 Weekly Construction Update
Work this week: General contractor placed HVAC units on the roof in the mechanical well. Construction team continued work on standing seam metal roof, and lathe and paper for the plaster. Holes for site light standards were augured. Substantial completion...
Download PDF →Early Childhood Education – 06-12-20 Weekly Construction Update
Work this week: General contractor worked on T-bar ceiling and ECE’s observation rooms. Construction team installed mirrored glass at the observation rooms. Roofing work and the lathe and paper that is the structural support for the plaster is ongoing.
Download PDF →Early Childhood Education – 06-05-20 Weekly Construction Update
Work this week: General contractor continued working on standing metal seam roof at the main building, and storage buildings. Painting remains ongoing. Plaster mock ups are in place at the south/west corner of the Building for architect review.
Download PDF →May 2020 Monthly Project Update
Monthly status update on all existing Measure L projects.
Download PDF →Early Childhood Education – 05-29-20 Weekly Construction Update
Work this week: General contractor continued working on utility rough ins, interior painting, and standing metal seam roof.
Download PDF →Early Childhood Education – 05-15-20 Weekly Construction Update
Work this week: General contractor continuing working on plumbing, mechanical rough ins, roofing, and window installation.
Download PDF →Early Childhood Education – 05-08-20 Weekly Construction Update
Work this week: General contractor continued working on plumbing, mechanical rough ins, and window installation.
Download PDF →