Early Childhood Education – 05-01-20 Weekly Construction Update
Work this week: General contractor continued work on rough ins, duct insulation, and window installation.
Download PDF →April 2020 Monthly Project Update
Monthly status update on all existing Measure L projects.
Download PDF →Early Childhood Education – 04-24-20 Weekly Construction Update
Work this week: The utility rough ins work remains ongoing. The metal roof mockup started and A/C curbs were welded.
Download PDF →Early Childhood Education – 04-17-20 Weekly Construction Update
Work this week: General contractor continued work on the utility rough ins. Window mockup have been completed, noise mitigating HVAC curbs were craned, and set in place.
Download PDF →Early Childhood Education – 03-27-20 Weekly Construction Update
Work this week: General contractor continued work on utility rough in, plumbing, gas line detailing, wall penetrations, and HVAC duct work.
Download PDF →Early Childhood Education – 03-20-20 Weekly Construction Update
Work this week: General contractor continued rough in work. The fabrication of the HVAC curb extenders was completed, and were set in the mechanical well. The window frame mock-ups are currently in review, awaiting approval.
Download PDF →Early Childhood Education – 03-13-20 Weekly Construction Update
Work this week: General contractor continued drywall and insulation work, as well as fabrication on the HVAC. Roughing ins and all the essential piping and ductwork remains ongoing. The window frame mock up work is complete and under review by...
Download PDF →Early Childhood Education – 03-06-20 Weekly Construction Update
Work this week: General contractor continued drywall and insulation install, as well as rough ins and plywood installation on the soffits. Window frame install work has been completed.
Download PDF →Early Childhood Education – 02-28-20 Weekly Construction Update
Work this week: General contractor is working on drywall rough ins and completing the building wrap. Construction team started work on the window frame install, and the soffit plywood and associated work.
Download PDF →Early Childhood Education – 02-21-20 Weekly Construction Update
Work this week: General contractor completed core drilling work on the main vault for the main electrical...
Download PDF →