Cuesta College Bond Info

  • About Measure L
    • General Info
    • Ballot Language
    • Frequently Asked Questions
  • Project Info
    • Project Overview
    • Projects: 1st Issuance
    • Projects: 2nd Issuance
    • Projects: 3rd Issuance
    • Projects: 4th Issuance
    • Featured Image Gallery
    • Construction Alerts
    • SLO Campus Map
    • North County Map
  • Oversight Committee
  • Business Opportunities
    • Contractor Prequalification
    • Business RFQs/RFPs
    • Bid Timelines
    • Online Plan Room
  • News
  • Contact

Category: NCC Early Childhood Education Center

Early Childhood Education – 05-01-20 Weekly Construction Update

May 1, 2020 · Construction Updates, NCC Early Childhood Education Center

Work this week: General contractor continued work on rough ins, duct insulation, and window installation.

Download PDF →

April 2020 Monthly Project Update

April 30, 2020 · Construction Updates, NCC Early Childhood Education Center

Monthly status update on all existing Measure L projects.

Download PDF →

Early Childhood Education – 04-24-20 Weekly Construction Update

April 24, 2020 · Construction Updates, NCC Early Childhood Education Center

Work this week: The utility rough ins work remains ongoing. The metal roof mockup started and A/C curbs were welded. 

Download PDF →

Early Childhood Education – 04-17-20 Weekly Construction Update

April 17, 2020 · Construction Updates, NCC Early Childhood Education Center

Work this week: General contractor continued work on the utility rough ins. Window mockup have been completed, noise mitigating HVAC curbs were craned, and set in place.

Download PDF →

Early Childhood Education – 03-27-20 Weekly Construction Update

March 27, 2020 · Construction Updates, NCC Early Childhood Education Center

Work this week: General contractor continued work on utility rough in, plumbing, gas line detailing, wall penetrations, and HVAC duct work.

Download PDF →

Early Childhood Education – 03-20-20 Weekly Construction Update

March 20, 2020 · Construction Updates, NCC Early Childhood Education Center

Work this week: General contractor continued rough in work. The fabrication of the HVAC curb extenders was completed, and were set in the mechanical well. The window frame mock-ups are currently in review, awaiting approval.

Download PDF →

Early Childhood Education – 03-13-20 Weekly Construction Update

March 13, 2020 · Construction Updates, NCC Early Childhood Education Center

Work this week: General contractor continued drywall and insulation work, as well as fabrication on the HVAC. Roughing ins and all the essential piping and ductwork remains ongoing. The window frame mock up work is complete and under review by...

Download PDF →

Early Childhood Education – 03-06-20 Weekly Construction Update

March 6, 2020 · Construction Updates, NCC Early Childhood Education Center

Work this week: General contractor continued drywall and insulation install, as well as rough ins and plywood installation on the soffits. Window frame install work has been completed.

Download PDF →

Early Childhood Education – 02-28-20 Weekly Construction Update

February 28, 2020 · Construction Updates, NCC Early Childhood Education Center

Work this week: General contractor is working on drywall rough ins and completing the building wrap. Construction team started work on the window frame install, and the soffit plywood and associated work.

Download PDF →

Early Childhood Education – 02-21-20 Weekly Construction Update

February 21, 2020 · Construction Updates, NCC Early Childhood Education Center

Work this week: General contractor completed core drilling work on the main vault for the main electrical...

Download PDF →
← Newer Posts
Older Posts →
  • Search News:

    Search the Cuesta College Bond Website:
  • News Categories

    • Articles
    • Construction Updates
      • 9100 Roofing-HVAC
      • District Wide Asphalt
      • District Wide Upgrades
      • District Wide Upgrades 2nd
      • District-Wide Wayfinding
      • EV Charging Stations
      • Hollister Adobe Stabilization
      • Interim Housing
      • NCC Campus-wide
      • NCC Early Childhood Education Center
      • NCC Parking Lot 10 and Monument Sign
      • North County Campus Center
      • North County Sitework
      • Planning – Aquatic Center
      • Repairs – HVAC/Roofs 1100, 4500, and 4600
      • SLO 1000 Complex Renovations
      • SLO 2000 Complex Renovations
      • SLO Campus Center
      • SLO Campus Center Design
      • SLO Campus Instructional Building
      • SLO Data Center
      • SLO HVAC/Roofs Phase 1
      • SLO HVAC/Roofs Phase 2
      • SLO Switchgear Replacement
      • Technology Upgrades 2nd
      • Technology Upgrades 3rd
      • Upgrades – Aquatic Center
    • Press Releases
    • Uncategorized

Back To Top

Cuesta College Logo
Search the Cuesta College Bond Website: