January 2017 Monthly Project Updates
Monthly status update on all existing Measure L projects.
Download PDF →North County Campus Center – 01-27-17 Weekly Construction Update
Work this week: The second floor slab on deck concrete was poured along with the last of the slab closure concrete pours which completes all of the building structural concrete...
Download PDF →North County Campus Center – 01-20-17 Weekly Construction Update
Work this week: The concrete contractor continued installation of reinforcing the second floor deck, completed formwork on the second floor depressed slab areas, and placed the slab-on-grade closure pour #3...
Download PDF →North County Campus Center – 01-13-17 Weekly Construction Update
Work this week: The concrete contractor continued installation of reinforcing at the second floor deck slab; continued formwork on the second floor and 1st floor block outs; and placed an additional slab on grade closure section...
Download PDF →North County Campus Center – 01-06-17 Weekly Construction Update
Work this week: The slab-on-grade reinforcing, edge forms, and vapor barrier are complete, and reinforcing is being installed on the second floor deck...
Download PDF →December 2016 Monthly Project Update
Monthly status update on all existing Measure L projects.
Download PDF →North County Campus Center – 12-23-16 Weekly Construction Update
Work this week: The plumbing, HVAC, and electrical contractors continue to install hanger inserts and pipe/conduit-penetration sleeves through the second floor decking...
Download PDF →North County Campus Center – 12-16-16 Weekly Construction Update
Work this week: The Plumbing, HVAC, and Electrical contractors have started to install hanger inserts and pipe/conduit penetration sleeves through the second floor decking...
Download PDF →North County Campus Center – 12-09-16 Weekly Construction Update
Work this week: The structural steel erector continues the installation of the mansard framing and has started the architectural louvers at the front entry...
Download PDF →North County Campus Center – 12-02-16 Weekly Construction Update
Work this week: The structural steel erector continues to weld structural steel beam connections...