North County Campus Center – 09-22-17 Weekly Construction Update
Work this week: Drywall installation, tape, texture, and finish continues on the 1st and 2nd floor with interior paint following along…
Work this week: Drywall installation, tape, texture, and finish continues on the 1st and 2nd floor with interior paint following along…
Work this week: Drywall installation has started at the computer lab skylight opening and continues throughout the building…
Work this week: Plaster, drywall, interior and exterior paint, and acoustical ceiling installation continue to progress…
In November of 2014, the voters of San Luis Obispo County passed Measure L, a $275 million general obligation bond, providing facility and infrastructure improvements and repairs to Cuesta College. Today, the first issuance projects totaling $75 million are nearing completion, while the second issuance plans ($72 million) are gearing up for action. The two […]
Work this week: Drywall, paint, and acoustical ceiling installation continue to progress and the K-13 spray acoustical insulation was complete in the in the main entry and the cafeteria…
Monthly status update on all existing Measure L projects.
Work this week: The standing-seam-metal roof at the high roof is complete…
Work this week: Installation of the standing seam roof at the high roof area began this week and is near completion…
Work this week: Plumbing, electrical, lighting, HVAC, access controls, and fire sprinkler rough-in work and testing continue; and the interior doors and windows are being installed…
Work this week: The plaster contractor continues to install lath, and has installed the scratch and brown coats on several areas of the building…