July 2017 Monthly Project Update
Monthly status update on all existing Measure L projects.
Monthly status update on all existing Measure L projects.
Work this week: The plaster contractor continues to install lath, and has started the first coat of plaster…
Work this week: Plumbing, electrical, HVAC, controls, fire alarm system, and audio visual systems rough-in work continues…
Work this week: The roofing contractor has completed the installation of the small single ply roof…
Work this week: The roofing contractor has started the installation of the small single-ply roof…
Monthly status update on all existing Measure L projects.
Work this week: The roofer has begun installing insulation and plywood on the high roof…
Work this week: The roofing contractor is finalizing the detail work at the main single ply roof and will be starting on the high metal roof next week…
Work this week: The roofing contractor is continuing the installation of the single ply roofing membrane at the main flat roof…
Work this week: The framing contractor is continuing to install drywall and insulation 1st and 2nd floors…