North County Campus Center – 11-17-17 Weekly Construction Update
Work this week: The curtain wall glazing in the main entry to the building is being installed…
Work this week: The curtain wall glazing in the main entry to the building is being installed…
Work this week: Mechanical, electrical, plumbing, acoustical ceilings, paint, drywall, tile, kitchen equipment installation continues…
Work this week: The landscape irrigation and the site-concrete layout and placement continue throughout the site. Installation of the kitchen equipment has begun…
Monthly status update on all existing Measure L projects.
Work this week: The installation of the elevator began this week…
Work this week: The project’s contractors continue to install piping and controls’ wiring for the HVAC equipment on the rooftop…
Work this week: Data and power cables are being pulled throughout various locations in the building. Installation of the curtain wall at the southern elevation has continued, and tile preparation and installation is scheduled to begin…
Work this week: Contractors continue the installation of the drywall, insulation, acoustical ceilings, HVAC, electrical, painting, communications, data and fire protection on the 1st and 2nd floors…
Monthly status update on all existing Measure L projects.
Work this week: Contractors continue the installation of the drywall, insulation, HVAC, electrical, painting, communications, Data and Fire Protection on the 1st and 2nd floors…