North County Campus Center – 01-26-18 Weekly Construction Update
Work this week: The plumbing contractor has continued to set finishes in the first floor restrooms…
Work this week: The plumbing contractor has continued to set finishes in the first floor restrooms…
Work this week: Plumbing, HVAC, electrical, acoustical plaster, communications, fire protection, drywall, glazing, tile, doors & hardware, painting, kitchen, and ceiling contractors continue to move forward on both floors of the building…
Work this week: The plumbing, HVAC, electrical, acoustical plaster, communications, fire protection, drywall, glazing, tile, doors & hardware, painting, kitchen, and ceiling contractors continue to move forward on both floors of the building.
Work this week: Installation of various ceilings throughout the building is progressing…
Monthly status update on all existing Measure L projects.
Work this week: The HVAC system was started up in order for the building to be conditioned…
Work this week: The skylight installation is complete, and the torsion spring ceiling grid at the high ceiling continues…
Work this week: The installation of the high ceiling continues, the skylight installation is near completion, and the curtain wall system is moving forward…
Work this week: A fair weather forecast allowed the skylight installation to continue, and the concrete at terrace deck was placed…
Work this week: Many of the trade contractors continue to work throughout the building…